Weather: Cloudy 81˚/61˚
Subs on Site
<TouchStone> (14)
<Red Oak> (8)
<DG Concrete> (3)
Work in Progress:

(Red Oak) finished forming Building 'E' Breeze way walls, passed inspection on Building 'E' walls and 'D' floor, and tied bar in Building 'A' garage floor. Then started forming Building 'B' footing
(DG Concrete) Dug the water way in Building 'A' parking lot. Started forming the sidewalk around Building 'C' and compacted the back fill they added around Building 'D'
Terri (Questar) came by and measured the services to the buildings we are going to try and get all off them installed so they do not have to bore under the road. We also drove to 500 South and laid out the two stubs their.