Monday 8/27/2012



Weather: Partly Cloudy  90˚/59˚

Subs on Site
<Sterns>                      (12)
<TouchStone>              (16)
<Red Oak>                 (7)
<DG Concrete>            (2)

Work in Progress:
(Sterns) poured the end sections were they could not slip.  Dennis (Sterns) noticed that the large island in Building 'A' parking lot had a transition across the sidewalk, at the handicap ramp on the North end,  of 1 foot.  I called Lonny (Legend) and we moved the stake in the small parking lot up .8' and the stake out by the road  .6'.  This will leave a channel in the road.

(TouchStone)Sheeted the 4th Floor

 (Red Oak)formed Building 'B' footings.

(DG Concrete) Back filled the interior of Building 'E' and touched up the grades for Sterns