Weather: Partly Cloudy 90˚/59˚
Subs on Site
<Sterns> (12)
<TouchStone> (16)
<Red Oak> (7)
<DG Concrete> (2)

(Sterns) poured the end sections were they could not slip. Dennis (Sterns) noticed that the large island in Building 'A' parking lot had a transition across the sidewalk, at the handicap ramp on the North end, of 1 foot. I called Lonny (Legend) and we moved the stake in the small parking lot up .8' and the stake out by the road .6'. This will leave a channel in the road.
(TouchStone)Sheeted the 4th Floor
(Red Oak)formed Building 'B' footings.
(DG Concrete) Back filled the interior of Building 'E' and touched up the grades for Sterns