Thursday 3/14/2013

Weather: Sunny 63˚/28˚ 

Subs on Site

<G&M Woods>                 (4)
<Wall to Wall>                  (4)
<Diamond Z>                    (3)
<Nutek>                            (11)
<Cardalls>                        (2)
<Warburtons>                  (8)
<Extreme Fire>                 (2)
<Air Doctors>                   (7)
<Reliance>                       (12)
<Red Oak Plumbing>       (4)

Work in Progress
(G&M Woods) Installed the cabinets in Building 'C' 2nd and 3rd floors on West end.

(Wall to Wall) Painted the patches on the 4th floor of the South Tower in Building 'A'.  There were 50 in just these four units.

(Diamond Z) Worked on Building 'D&E' stone.

(Nutek) Hung finished sheetrock in Building 'E'.  The tapers touched up Building 'A' North Tower..  . 

(Warburtons) Worked on the South side entry gables of Building 'C'.  Worked on the North side of Building 'D'. They also finished all of the roofs.

(Air Doctors) Finished pre rough for 1st floor in Building 'B'.  They tried to set the Condencers but the pads that DG Concrete graded were not big enough. 

(Reliance) Wiring Building 'B'.

(Red Oak) Fire caulked Building 'B'  Finished the punch list on Building 'A'.



Wednesday 3/13/2013

Weather: Sunny 55˚/27˚ 

Subs on Site

<Wall to Wall>                  (4)
<SBS>                              (4)
<Diamond Z>                    (3)
<Nutek>                            (11)
<Cardalls>                        (2)
<Warburtons>                  (8)
<Extreme Fire>                 (2)
<Air Doctors>                   (4)
<Reliance>                       (12)
<Red Oak Plumbing>       (1)
<DG Concrete>                (2)


Work in Progress
Outback Rentals came out to repair the lift and the pin that holds the new ram to the forks would not go through the bent bracket.  We are going to rent a lift for now and buy a new bracket. 

(Wall to Wall) Painted 1st floor Building 'D'.

(SBS) Worked on trim on 3rd floor of Building 'D' then started hardware in Building 'C'

(Diamond Z) Worked on Building 'E' stone.

(Nutek) Hung the sheetrock in Building 'E' 3rd floor.  The tapers touched up Building 'A' 3rd and 4th floor South end.  . 

(Warburtons) Worked on the South side entry gables of Building 'C'.  Worked on the North side of Building 'D'.

(Air Doctors) Finished pre rough for 1st floor in Building 'B'

(Reliance) Wiring Building 'B'.

(Red Oak) Fire caulked Building 'B'  Found and fixed another leak in Building 'A' 403. .

(DG Concrete) graded the pads for the condensers. 

Tuesday 3/12/2013

Weather: Sunny 49˚/27˚ 

Subs on Site
<SBS>                              (4)
<Diamond Z>                    (3)
<Nutek>                            (11)
<Cardalls>                        (2)
<Warburtons>                  (8)
<Extreme Fire>                 (2)
<Air Doctors>                   (4)
<Reliance>                       (12)
<Red Oak Plumbing>       (1)

Work in Progress
(Wall to Wall) Primed 1st floor Building 'D'.

(SBS) Worked on trim on 3rd floor of Building 'D' then started hardware in Building 'C'

(Diamond Z) Worked on Building 'E' stone.

(Nutek) Hung the sheetrock in Building 'E' 4th floor.  The tapers touched up Building 'A' 3rd and 4th floor South end.  They textured 4th floor in Building 'D'. . 

(Warburtons) Worked on the South side entry gables of Building 'C'.  Worked on the North side of Building 'D'.

(Air Doctors) Installed the exhaust vents on the Water heaters in Building 'A'

(Reliance) Wiring Building 'B'.

(Red Oak) Fire caulked Building 'B'.  We found one a tub that would not drain in A208..



Monday 3/11/2013

Weather: Sunny 44˚/24˚ 

Subs on Site
<Wall to Wall>                  (4)
<SBS>                              (4)
<Diamond Z>                    (3)
<Nutek>                            (11)
<Warburtons>                  (6)
<Air Doctors>                   (4)
<Reliance>                       (12)
<Red Oak Plumbing>       (1)

Work in Progress
(Wall to Wall) Prepped 1st floor Building 'D'.

(SBS) Worked on trim on 3rd floor of Building 'D'

(Diamond Z) Worked on Building 'E' stone.

(Nutek) Hung the sheetrock in Building 'E'.  The tapers did not work on Building 'A' on Thursday and Friday.  The Painters were able to start on Building 'D' while they wait to touch up Building 'A'. They will repaire Building 'A' so that the painters can touch up on Wednesday. 

(Warburtons) Worked on the West side of Building 'C' but their lift would not start today.  Worked on the East side of Building 'D'.

(Air Doctors) Worked on the flex ducts 3rd and 4th floors Building 'E' and passed inspection on 3rd and 4th floors  fire caulk.

(Reliance) Wiring Building 'B'.

(Red Oak) Past fire caulk inspection on Building 'E'.  Started fire caulking Building 'B'.  We found one more leak in unit 403.



Sub Meeting 3/11/2013

Bryson (Reliance)
Rob (Wall to Wall)
Ryan (SBS)
Eric (Nutek)

Talking Points:
Track out and Mud: Each contractor is responsible for their own track out both into the street and onto our lot.
Curbs are soft: With all of the melt the curbs are soft and I ask that no one drive over the curbs without a dirt ramp.
Heaters:  We will be turning the heaters off during the day and night unless the drywaller or painter needs them to dry.
Building ‘A’ Nutek will tape the patches and touch up for ‘A’ today and into tomorrow.  Rob (Wall to Wall) will start touch-up paint on Wednesday.
Building ‘C’  Vinyl will start on Wednesday 3/13.  They will have 2 or 3 units ready by 10 AM so that (G&M Woods) can start cabinet install on 2nd, 3rd, and 4th floors Wednesday 3/13 behind them..
Building ‘D’ 4th floor should be textured by 3/12 with sand and touch-up on Wednesday 3/13.   Finish work will be comple on 3rd floor for the painter to start by mid-day tomorrow 3/12.
Building ‘E’  Fire caulk inspection passed for 3rd and 4th floors today.  Flex ducts should be complete tonight for the entire Building.  Fire sprinklers are only trimmed in 2 ½ units on 1st floor they will try to get here tomorrow or Wednesday to cut the remainder of the Building.
Building ‘B’  Bryson (Reliance) said they will be able to have the whole of Building ‘A’ ready for 4-way Monday 3/18 and a majority for our 4-way on Thursday 3/14.  The insulators will start on Monday 3/18.  


Schedule:
Building ‘A’
Final inspection 3/13
HUD inspection 3/20
Building ‘C’
2nd, 3rd and 4th floor Vinyl 3/14
2nd, 3rd, and 4th floor Cabinets start 3/14
Building ‘D’
4th floor Drywall textured 3/13.
3rd Floor Finish work complete 3/13.
4th Floor Finish work complete 3/15.

1st and 2nd  floor Paint starts  3/11 complete 3/22.

Building ‘E’
Fire Caulk inspection 3/11.
Flex ducts installed 3/11.
Drywall starts 3/11.
Gypcrete 3/21.
Building ‘B’
4-way inspection 3/14.
Insulation starts 3/18.


Thursday 3/7/2013


Weather: Sunny 38˚/14˚ 

Subs on Site
<Knell>                             (7)
<SBS>                              (8)
<Diamond Z>                    (3)
<Nutek>                            (11)
<Warburtons>                  (11)
<Air Doctors>                   (3)
<Reliance>                       (12)
<Red Oak Plumbing>       (2)

Work in Progress
(Knell)  Cleaned their sand piles from previous pours and then poured Building 'D'

(SBS) Worked on hardware for Building 'A'.  Worked on trim on 1st floor of Building 'D' and installed the steel doors,on Building 'B'.  Joe (SBS) and Eric (Nutek) discussed the steel doors.  The installers were not leaving enough space to get the 5/8" drywall behind the jams.  They will now use spacers on all four corners when they hang them.

(Diamond Z) Moved over to Building 'E' stone while the gypcrete was being poured on Building 'D'.

(Nutek) Hung the sheetrock in the breeze way lids of Building 'D' and 'E'.  They also touched up and repaired Building 'A' so that the painters can touch up on Monday.. 

(Warburtons) Worked on the West side of Building 'C' and the 4th floor West patios.  Worked on the East side of Building 'D' as well as the patios on 1st floor.

(Air Doctors) Worked on the Hard ducts on 3rd and 4th floors Building 'E' and passed inspection on 1st and 2nd floors  fire caulk.

(Reliance) Wiring Building 'B'.

(Red Oak) Past fire caulk inspection on Building 'E'.  Cleaned out Building 'A'   



.

Wednesday 3/6/2012


Weather: Sunny 38˚/14˚ 

Subs on Site
<Sterns>                           (8)
<SBS>                              (8)
<Diamond Z>                    (3)
<Nutek>                            (11)
<Warburtons>                  (11)
<Air Doctors>                   (3)
<Reliance>                       (8)
<Red Oak Plumbing>       (6)
<DG Concrete>                (1)
<JP Steel>                        (2)

Work in Progress
(Sterns) Stripped the forms and cleaned the building.  

(SBS) Worked on hardware for Building 'A'.  Worked on trim on 1st floor of Building 'D' and installed the patio steel doors,

(Diamond Z) Laid stone on the entry gables of Building 'D'.

(Nutek) Sanded the texture 2nd and 3rd floor of Building 'D'.  Hung and taped drywall on the 4th floor of Building 'D'. 

(Warburtons) Worked on the West side of Building 'C' and the 4th floor West patios.  Worked on the East side of Building 'D' as well as the patios on 1st floor.

(Air Doctors) Worked on the Hard ducts on 3rd and 4th floors Building 'E'.   They fail the fire caulk inspection.

(Reliance) Wiring Building 'B'.

(Red Oak) Failed fire caulk inspection on Building 'E'.  Turned the water on for the North tower of Building 'A'.  They found one more unit with the Hot and Cold switched.  

(DG Concrete) Back filled the window wells on Building 'A' for the condenser pads.  He also broke out the ice for the entry pads on Building 'A's West side. 

(JP Steel) installed the last 2 window wells for Building 'A'.




Tuesday 3/5/2013


Weather: Partly Cloudy 35˚/11˚ 

Subs on Site
<Sterns>                           (8)
<Clegg Steel>                   (6)
<SBS>                              (8)
<Diamond Z>                    (3)
<Nutek>                            (11)
<Warburtons>                  (11)
<Air Doctors>                   (3)
<Reliance>                       (8)
<Red Oak Plumbing>       (6)
<DG Concrete>                (1)
<JP Steel>                        (2)

Work in Progress
(Sterns) Poured the corridors and decks on Building 'D'.  The concrete pump burst a pipe and sprayed concrete all over the Building's exterior.  Mario and Curtis swept and then hosed of the entry roof.

(Clegg Steel) Used Reliance's lift and Installed stairs in Building 'B' and the chimney caps on Building 'A'.  They also worked on some detail work on the stair handrails for Building 'A'.

(SBS) Worked on hardware and unboxed all of the appliances for Building 'A'. Started trim on 1st floor of Building 'D'

(Diamond Z) Laid stone on the entry gables of Building 'D' 
(Nutek) Textured 2nd and 3rd floor of Building 'D'.  Hung and taped drywall pre-rock on the 4th floor of Building 'E'. 

(Warburtons) Worked on the West side of Building 'C' and the 4th floor West patios.  Started on the East side of Building 'D'

(Air Doctors) Worked on the Hard ducts on 2nd and 3rd floor Building 'E'. 

(Reliance) Continued Cleaning Building 'B' and wiring Building 'B'.

(Red Oak) Investigated and found the leak under the slab in Building 'D'.  They turned on the water in the South tower of Building 'A' and found a leak in one unit and 2 units with the hot and cold water switched.  We tried to turn on the water in the North tower but found the setter was frozen.  

(DG Concrete) Delivered our Backhoe. Had to cut into the valve box in order to get the meter set on both off Building 'A's meters.  He also dug out for the window wells on Building 'A'.

(JP) Steel installed 12 of the 14 window wells for Building 'A'.




Monday 3/4/2013


Weather: Partly Cloudy 39˚/18˚ 

Subs on Site
<Sterns>                           (4)
<SBS>                              (8)
<Diamond Z>                    (3)
<Nutek>                            (11)
<Warburtons>                  (11)
<Air Doctors>                   (3)
<Reliance>                       (8)
<Red Oak Plumbing>       (6)

Work in Progress
(Sterns) Formed and installed water proofing for their corridors and decks on Building 'D'

(SBS) Worked on hardware and unboxed all of the appliances for Building 'A'.  Hung Steel doors on Building 'E'

(Diamond Z) Laid stone on the East side of Building 'D' 

(Nutek) Taped 2nd and 3rd floor of Building 'D'.  Hung drywall pre-rock on the 3rd floor of Building 'E'. 

(Warburtons) Worked on the North side of Building 'C' and the 4th floor East breezeway.  They continued on the South side of Building 'D'

(Air Doctors) Worked on the Hard ducts on 2nd floor Building 'E'. 

(Reliance) Cleaned Building 'B' before starting on the panels and feeders on Building 'B'

(Red Oak) Finished Installing trim on the North tower Building 'A'.  Passed inspection for gas and DWV on the Club House. Ether found a leak under the slab in Building 'D'.  He had Sterns cut the slab and will investigate tomorrow.


Sub Meeting 3/4/2013


Rick (Warburtons)
Bryson (Reliance)
William (Air Doctors)
Rob (Wall to Wall)
Ryan (SBS)

Talking Points:
Track out and Mud: Each contractor is responsible for their own track out both into the street and onto our lot.
Curbs are soft: With all of the melt the curbs are soft and I ask that no one drive over the curbs without a dirt ramp.
Heaters:  We will be turning the heaters off during the day and on low at night unless the drywaller or painter needs them to dry.
Building ‘A’ Ether needs meters for water test.  Air Doctors will hook up the condensers and water heater vents next week.
Building ‘C’  Rob (Wall to Wall) said they will finish paint on all of the building this week.  Vinyl will start on Monday 3/11.   (G&M Woods) will start cabinet install on 2nd, 3rd, and 4th Thursday 3/14.
Building ‘D’ 2nd floor should be textured by 3/5.  Gypcrete will be poured on Thursday 3/7. The Corridors will be poured Tuesday 3/5.   Finish work will be comple on first and 2nd floor for the painter to start on Monday 3/11.
Building ‘E’  Prerock will be complete on Tuesday 3/5/2013.  Framers will start on Wednesday 3/6.  Fire caulk inspection is set for 3/6.  Flex ducts should be complete on 3/6 for Drywall to start hanging on 3/7.
Building ‘B’  Bryson (Reliance) said that they have more man power coming this week and they will be able to have the whole of Building ‘A’ ready for 4-way on Thursday 3/14.  They may be able to have part of the building ready before then.  The insulators will start on Monday 3/18.  I will check to see if they can come earlier to get started.  


Schedule:
Building ‘A’
Final inspection 3/14
Building ‘C’
3rd and 4th floor paint started 3/4
2nd, 3rd and 4th floor Vinyl 3/11
2nd, 3rd, and 4th floor Cabinets start 3/14
Building ‘D’
Corridors poured 3/5
1st floor finish starts  3/5
2nd floor Drywall textured 3/6.
3rd floor  Drywall textured 3/7.
Gypcrete 3/7.
Paint Starts 3/11
Building ‘E’
Pre Rock complete 3/5/2013
Fire Caulk inspection 3/6
Drops framed 3/6 - 3/9
Drywall might start 3/7
Building ‘B’
4-way inspection 3/14.
Insulation starts 3/18.



Friday 3/1/2013


Weather: Partly Cloudy 35˚/14˚ 

Subs on Site
<Wholesale Flooring>      (7)
<SBS>                              (8)
<Diamond Z>                    (3)
<Nutek>                            (11)
<Extreme Fire>                 (4)
<Warburtons>                  (11)
<Air Doctors>                   (3)
<Reliance>                       (6)
<Red Oak Plumbing>       (6)

Work in Progress
(Wholesale Flooring) Installed carpet on the 3rd and 4th floor of the North Tower Building 'A' 

(SBS) Trimed in the units on the East side of the 3rd and 4th floor of Building 'C', worked on hardware and unboxed all of the appliances for Building 'A'. 

(Diamond Z) Laid stone on the East side of Building 'D' and Continued to lay stone on the South West side of Building 'E'.

(Nutek) Taped 2nd and 3rd floor of Building 'D'.  Hung drywall pre-rock on the 2nd floor of Building 'E'.  Taped the 2nd floor pre rock Building 'E'

(Extreme Fire) Worked on Building 'B's attic system.  

(Warburtons) Worked on the North side of Building 'C' and the 4th floor East breezeway.  They continued on the South side of Building 'D'

(Air Doctors) Worked on the Hard ducts on 1st floor Building 'E'. 

(Reliance) Trouble shot the parking lot lights for Building 'A'.  Installed the emergency lights for Building 'A'.

(Red Oak) Finished Installing trim on the North tower Building 'A'r.  They will have the Club House plumbed by Monday.  
.