Wednesday 3/13/2013

Weather: Sunny 55˚/27˚ 

Subs on Site

<Wall to Wall>                  (4)
<SBS>                              (4)
<Diamond Z>                    (3)
<Nutek>                            (11)
<Cardalls>                        (2)
<Warburtons>                  (8)
<Extreme Fire>                 (2)
<Air Doctors>                   (4)
<Reliance>                       (12)
<Red Oak Plumbing>       (1)
<DG Concrete>                (2)


Work in Progress
Outback Rentals came out to repair the lift and the pin that holds the new ram to the forks would not go through the bent bracket.  We are going to rent a lift for now and buy a new bracket. 

(Wall to Wall) Painted 1st floor Building 'D'.

(SBS) Worked on trim on 3rd floor of Building 'D' then started hardware in Building 'C'

(Diamond Z) Worked on Building 'E' stone.

(Nutek) Hung the sheetrock in Building 'E' 3rd floor.  The tapers touched up Building 'A' 3rd and 4th floor South end.  

(Warburtons) Worked on the South side entry gables of Building 'C'.  Worked on the North side of Building 'D'.

(Air Doctors) Finished pre rough for 1st floor in Building 'B'

(Reliance) Wiring Building 'B'.

(Red Oak) Fire caulked Building 'B'  Found and fixed another leak in Building 'A' 403. .

(DG Concrete) graded the pads for the condensers.