Weather: Sunny 38˚/14˚
Subs on Site
<SBS> (8)
<Diamond Z> (3)
<Nutek> (11)
<Warburtons> (11)
<Air Doctors> (3)
<Air Doctors> (3)
<Reliance> (12)
<Red Oak Plumbing> (2)
Work in Progress
(Knell) Cleaned their sand piles from previous pours and then poured Building 'D'
(SBS) Worked on hardware for Building 'A'. Worked on trim on 1st floor of Building 'D' and installed the steel doors,on Building 'B'. Joe (SBS) and Eric (Nutek) discussed the steel doors. The installers were not leaving enough space to get the 5/8" drywall behind the jams. They will now use spacers on all four corners when they hang them.
(SBS) Worked on hardware for Building 'A'. Worked on trim on 1st floor of Building 'D' and installed the steel doors,on Building 'B'. Joe (SBS) and Eric (Nutek) discussed the steel doors. The installers were not leaving enough space to get the 5/8" drywall behind the jams. They will now use spacers on all four corners when they hang them.
(Diamond Z) Moved over to Building 'E' stone while the gypcrete was being poured on Building 'D'.
(Nutek) Hung the sheetrock in the breeze way lids of Building 'D' and 'E'. They also touched up and repaired Building 'A' so that the painters can touch up on Monday..
(Warburtons) Worked on the West side of Building 'C' and the 4th floor West patios. Worked on the East side of Building 'D' as well as the patios on 1st floor.
(Air Doctors) Worked on the Hard ducts on 3rd and 4th floors Building 'E' and passed inspection on 1st and 2nd floors fire caulk.