Friday 3/1/2013


Weather: Partly Cloudy 35˚/14˚ 

Subs on Site
<Wholesale Flooring>      (7)
<SBS>                              (8)
<Diamond Z>                    (3)
<Nutek>                            (11)
<Extreme Fire>                 (4)
<Warburtons>                  (11)
<Air Doctors>                   (3)
<Reliance>                       (6)
<Red Oak Plumbing>       (6)

Work in Progress
(Wholesale Flooring) Installed carpet on the 3rd and 4th floor of the North Tower Building 'A' 

(SBS) Trimed in the units on the East side of the 3rd and 4th floor of Building 'C', worked on hardware and unboxed all of the appliances for Building 'A'. 

(Diamond Z) Laid stone on the East side of Building 'D' and Continued to lay stone on the South West side of Building 'E'.

(Nutek) Taped 2nd and 3rd floor of Building 'D'.  Hung drywall pre-rock on the 2nd floor of Building 'E'.  Taped the 2nd floor pre rock Building 'E'

(Extreme Fire) Worked on Building 'B's attic system.  

(Warburtons) Worked on the North side of Building 'C' and the 4th floor East breezeway.  They continued on the South side of Building 'D'

(Air Doctors) Worked on the Hard ducts on 1st floor Building 'E'. 

(Reliance) Trouble shot the parking lot lights for Building 'A'.  Installed the emergency lights for Building 'A'.

(Red Oak) Finished Installing trim on the North tower Building 'A'r.  They will have the Club House plumbed by Monday.  
.