Weather: Partly Cloudy 35˚/11˚
Subs on Site
<Clegg Steel> (6)
<SBS> (8)
<Diamond Z> (3)
<Nutek> (11)
<Warburtons> (11)
<Air Doctors> (3)
<Air Doctors> (3)
<Reliance> (8)
<Red Oak Plumbing> (6)
<DG Concrete> (1)
<JP Steel> (2)
<DG Concrete> (1)
<JP Steel> (2)
Work in Progress
(Sterns) Poured the corridors and decks on Building 'D'. The concrete pump burst a pipe and sprayed concrete all over the Building's exterior. Mario and Curtis swept and then hosed of the entry roof.
(Clegg Steel) Used Reliance's lift and Installed stairs in Building 'B' and the chimney caps on Building 'A'. They also worked on some detail work on the stair handrails for Building 'A'.
(SBS) Worked on hardware and unboxed all of the appliances for Building 'A'. Started trim on 1st floor of Building 'D'
(Clegg Steel) Used Reliance's lift and Installed stairs in Building 'B' and the chimney caps on Building 'A'. They also worked on some detail work on the stair handrails for Building 'A'.
(SBS) Worked on hardware and unboxed all of the appliances for Building 'A'. Started trim on 1st floor of Building 'D'
(Diamond Z) Laid stone on the entry gables of Building 'D'
(Nutek) Textured 2nd and 3rd floor of Building 'D'. Hung and taped drywall pre-rock on the 4th floor of Building 'E'.
(Warburtons) Worked on the West side of Building 'C' and the 4th floor West patios. Started on the East side of Building 'D'
(Air Doctors) Worked on the Hard ducts on 2nd and 3rd floor Building 'E'.
(Red Oak) Investigated and found the leak under the slab in Building 'D'. They turned on the water in the South tower of Building 'A' and found a leak in one unit and 2 units with the hot and cold water switched. We tried to turn on the water in the North tower but found the setter was frozen.
(DG Concrete) Delivered our Backhoe. Had to cut into the valve box in order to get the meter set on both off Building 'A's meters. He also dug out for the window wells on Building 'A'.
(JP) Steel installed 12 of the 14 window wells for Building 'A'.