Thursday 3/14/2013

Weather: Sunny 63˚/28˚ 

Subs on Site

<G&M Woods>                 (4)
<Wall to Wall>                  (4)
<Diamond Z>                    (3)
<Nutek>                            (11)
<Cardalls>                        (2)
<Warburtons>                  (8)
<Extreme Fire>                 (2)
<Air Doctors>                   (7)
<Reliance>                       (12)
<Red Oak Plumbing>       (4)

Work in Progress
(G&M Woods) Installed the cabinets in Building 'C' 2nd and 3rd floors on West end.

(Wall to Wall) Painted the patches on the 4th floor of the South Tower in Building 'A'.  There were 50 in just these four units.

(Diamond Z) Worked on Building 'D&E' stone.

(Nutek) Hung finished sheetrock in Building 'E'.  The tapers touched up Building 'A' North Tower..  

(Warburtons) Worked on the South side entry gables of Building 'C'.  Worked on the North side of Building 'D'. They also finished all of the roofs.

(Air Doctors) Finished pre rough for 1st floor in Building 'B'.  They tried to set the Condencers but the pads that DG Concrete graded were not big enough. 

(Reliance) Wiring Building 'B'.

(Red Oak) Fire caulked Building 'B'  Finished the punch list on Building 'A'.