Weather: Sunny 38˚/14˚
Subs on Site
<SBS> (8)
<Diamond Z> (3)
<Nutek> (11)
<Warburtons> (11)
<Air Doctors> (3)
<Air Doctors> (3)
<Reliance> (8)
<Red Oak Plumbing> (6)
<DG Concrete> (1)
<JP Steel> (2)
<DG Concrete> (1)
<JP Steel> (2)
Work in Progress
(Sterns) Stripped the forms and cleaned the building.
(SBS) Worked on hardware for Building 'A'. Worked on trim on 1st floor of Building 'D' and installed the patio steel doors,
(SBS) Worked on hardware for Building 'A'. Worked on trim on 1st floor of Building 'D' and installed the patio steel doors,
(Diamond Z) Laid stone on the entry gables of Building 'D'.
(Nutek) Sanded the texture 2nd and 3rd floor of Building 'D'. Hung and taped drywall on the 4th floor of Building 'D'.
(Warburtons) Worked on the West side of Building 'C' and the 4th floor West patios. Worked on the East side of Building 'D' as well as the patios on 1st floor.
(Air Doctors) Worked on the Hard ducts on 3rd and 4th floors Building 'E'. They fail the fire caulk inspection.
(Red Oak) Failed fire caulk inspection on Building 'E'. Turned the water on for the North tower of Building 'A'. They found one more unit with the Hot and Cold switched.
(DG Concrete) Back filled the window wells on Building 'A' for the condenser pads. He also broke out the ice for the entry pads on Building 'A's West side.
(JP Steel) installed the last 2 window wells for Building 'A'.