Subs on Site
<Diamond Z> (3)
<Nutek> (11)
<Cardalls> (2)
<Warburtons> (8)
<Extreme Fire> (2)
<Air Doctors> (4)
<Warburtons> (8)
<Extreme Fire> (2)
<Air Doctors> (4)
<Reliance> (12)
<Red Oak Plumbing> (1)
Work in Progress
(Wall to Wall) Primed 1st floor Building 'D'.
(SBS) Worked on trim on 3rd floor of Building 'D' then started hardware in Building 'C'
(SBS) Worked on trim on 3rd floor of Building 'D' then started hardware in Building 'C'
(Diamond Z) Worked on Building 'E' stone.
(Nutek) Hung the sheetrock in Building 'E' 4th floor. The tapers touched up Building 'A' 3rd and 4th floor South end. They textured 4th floor in Building 'D'. .
(Warburtons) Worked on the South side entry gables of Building 'C'. Worked on the North side of Building 'D'.
(Air Doctors) Installed the exhaust vents on the Water heaters in Building 'A'