Thursday 6/13/2013

Weather: Sunny  91˚/59˚   

Subs on Site
<Huskies>                        (5)
<Green Clean>                (2)
<Wall to Wall>                  (4)
<G&M Woods>                 (2)
<Reliance>                       (2)
<Red Oak>                     (2)

Work in Progress
(Huskies) Started final grade around Building 'B'.

(Green Clean)  Rough clean of Building 'B'.

(Wall to Wall) Painted the body on the South, West and North side of Building 'E' exterior.  Rob decided to repair the Back flow preventer that he hit with his lift. Rather than pay the $551 Huskies would charge.


(G&M Wood) Installed the counter tops in the Clubhouse and caulked the counter tops in 'B"

(Reliance) Trimed and tested Building 'B'.

(Red Oak)Install the last 16 kitchen sinks and started on the water heater drains

We had final inspection.  Aaron just noted that we were not ready and that all plumbing needed to be inspected again. 





Wednesday 6/12/2013

Weather: Sunny  91˚/59˚   

Subs on Site
<Huskies>                        (5)
<Green Clean>                (2)
<Wall to Wall>                  (4)
<SBS>                              (3)
<Reliance>                       (2)
<Elite Structures>             (2)
<Red Oak>                     (5)

Work in Progress
(Huskies) Trenched around Building 'B' and the Club House.

(Green Clean)  Rough clean of Building 'B'.

(Wall to Wall) Painted the body on the East side of Building 'E' exterior.

(SBS) Installed hardware and mirrors in Building 'B',  

(Reliance) Trimed and tested Building 'B'.

(Elite Structures) Set their frames, painted and installed the covers.  They left before they got the trim installed because Shane;s Dad had a heart attack.

(Red Oak) Installed 16 Kitchen sinks in the North Tower.  Turned on water on to the North Tower.   Their Bath tub trims did not come today.  Ether completed the punch list for the other buildings and left for Agrium 

Tuesday 6/12/2013

Weather: Sunny  89˚/53˚   

Subs on Site
<Huskies>                        (4)
<Green Clean>                (2)
<Wall to Wall>                  (4)
<SBS>                              (2)
<Reliance>                       (4)
<Elite Structures>             (2)
<Red Oak>                     (3)

Work in Progress
(Huskies) Trenched around Building 'B'.

(Green Clean)  Cleaned Building 'E'.  Started rough clean of Building 'B'.

(Wall to Wall) Caulked Building 'E' exterior.

(SBS) Installed hardware in Building 'B',  Started on Mirrors.

(Reliance) Trimed and tested Building 'B' and finished wiring for fire alarm.

(Elite Structures) Drilled for their footings at Building 'C', passed inspection, and poured them.

(Red Oak) Installed 16 Kitchen sinks in the South Tower.


Monday 6/10/2013

Weather: Sunny  97˚/56˚   

Subs on Site
<Huskies>                        (4)
<Green Clean>                (2)
<Wall to Wall>                  (4)
<SBS>                              (2)
<Reliance>                       (2)
<Air Doctors>                    (2)

Work in Progress
(Huskies) Trenched around Building 'B'.

(Green Clean)  Cleaned Building 'E'.  Started rough clean of Building 'B'.

(Wall to Wall) Caulked Building 'E' exterior.

(SBS) Installed hardware in Building 'B',

(Reliance) Trimed and tested Building 'B' and started wiring for fire alarm.

(Air Doctors) Installed the condensers for Building 'B'. Installed trim in the Club House.  Cleaned out the garges they had been using for storage.

The fire department was called at 9:45 pm by a tamper alarm.  The antifreeze system was not turned on for Building 'E'.  When I turned it on we discovered that there was a valve missing and we could not turn on the sprinklers for the attic without it being installed.




Thursday 6/6/2013

Weather: Partly Cloudy  83˚/52˚   

Subs on Site
<Huskies>                        (3)
<Green Clean>                (2)
<Wholesale Flooring        (4)
<Wall to Wall>                  (3)
<SBS>                              (1)
<Warburtons>                  (3)
<Reliance>                       (2)
<Air Doctors>                    (2)
<Red Oak>                       (3)
<DG Concrete>                (3)

Work in Progress
(Huskies) Trenched around Building 'B'.  Behind DG Concrete with sidewalk prep.

(Green Clean)  Cleaned Building 'E'.

(Wholesale Flooring) Installed carpet in Building 'B' South Tower.

(Wall to Wall) Painted the remainder of the exterior body on Building 'D'.   Stripped the masking and cleaned up.

(SBS) Installed hardware in Building 'B',

(Warburtons) Installed the Rain gutters on D.  

(Reliance) Trimed and tested Building 'B' and started wiring the condensers.

(Air Doctors) Installed the condensers for Building 'B'. Installed the furnaces in the Club House

(Red Oak) Installing their trim in Building 'B'.  

(DG Concrete) Graded and road based the sidewalks around the Club House.










Wednesday 6/5/2013

Weather: Partly Cloudy / 83˚/43˚   

Subs on Site
<Huskies>                        (3)
<Green Clean>                (2)
<Wholesale Flooring        (5)
<Wall to Wall>                  (3)
<SBS>                              (3)
<Warburtons>                  (6)
<Clegg Steel>                   (6)
<Air Doctors>                    (2)
<Red Oak>                       (3)
<DG Concrete>                (3)

Work in Progress
(Huskies) Trenched around Building 'B'.  Behind DG Concrete with sidewalk prep.

(Green Clean)  Cleaned Building 'E'.

(Wholesale Flooring) Installed the tack strip and delivered his carpet.

(Wall to Wall) Painted the body on Building 'D'.  Painted the Club House.

(SBS) Installed hardware in Building 'B',

(Warburtons) Installed the Rain gutters on D.  The siding guys worked on my punch list for Building 'B'.

(Clegg Steel) Installed the cut down chimney caps and painted the PVC pipes on A and C.

(Air Doctors) Installed the condensers for Building 'B'.

(Red Oak) Installing their trim in Building 'B'.  

(DG Concrete) Graded for the sidewalks in front of the Club House.






Tuesday 6/4/2013

Weather: Partly Cloudy / Windy 88˚/48˚   

Subs on Site
<Precision Asphalt>        (2)
<Huskies>                        (3)
<Green Clean>                (2)
<Wall to Wall>                  (3)
<SBS>                              (3)
<Cardalls>                        (2)
<Warburtons>                  (3)
<Clegg Steel>                   (6)
<Air Doctors>                    (2)
<Sterns>                           (6)
<Red Oak>                       (3)
<DG Concrete>                (3)

Work in Progress
(Precision Asphalt) Striped around Buildings 'D' and 'E'.  They started to lay out for Building 'B' stripes and discovered that the lot is 4 feet more narrow against the dumpster then at the entrance.  Their stalls will not fit and meet code.

(Huskies) Started trenching around Building 'B'.  Behind DG Concrete with sidewalk prep.

(Green Clean)  Touch up on Building 'D'.  Started back on 'E'.

(Wall to Wall) Painted the trim on Building 'D'.   Started caulking and touch up on C while the trim set up.

(SBS) Stocked the fridges in Building 'B', however the ranges and dishwashers did not come.  Scott (Home Depot) could on track them down before end of business day.. 

(Cardalls) Blew in the insulation in Building 'B' then the Club House and met with Corey (IECC) inspector and touched up 'D' again.

(Warburtons) Installed the Rain gutters on B and C garages and touched up the fascia on A.

(Clegg Steel) Installed the cut down chimney caps and painted the PVC pipes on B, D, and E. and continued on Handrails in 'B'.

(Air Doctors) Installed the condensers for Building 'B'.

(Sterns) Poured sidewalk around 'E' and some in front of Building 'B'.

(Red Oak) Finished the last of Building 'E' inspection items under the inspectors nose then started installing their trim in Building 'B'.  

(DG Concrete) Installed the road base under all of Building 'B' sidewalks.




Monday 6/3/2013

Weather: Partly Cloudy / Windy 84˚/48˚   

Subs on Site
<Precision Asphalt>        (2)
<Huskies>                        (3)
<Green Clean>                (2)
<Wall to Wall>                  (3)
<Cardalls>                        (2)
<Warburtons>                  (3)
<Air Doctors>                    (2)
<Red Oak>                       (3)
<DG Concrete>                (3)

Work in Progress
(Precision Asphalt)  Laid out the strips around Buildings 'D' and 'E'.

(Huskies) Started trenching around Building 'B'.

(Green Clean)  Touch up on Building 'D'.

(Wall to Wall) Tried to Paint the trim on Building 'D' but it was too windy.   They Primed the Club House.

(Cardalls) Blew in the insulation in Building 'B' and met with Corey (IECC) inspector and touched up 'D' and 'E'.

(Warburtons) Installed the Rain gutters on Building 'C'.

(Air Doctors) Installed the condensers for Building 'B'.

(Red Oak) Stocked their trim in Building 'B'.  Then started on the inspection list for Building 'E'.  Standard did not have the clean out cover and Wynneilsons was close so they will finish in the morning.

(DG Concrete) Graded the west side of Building 'B' for rock walls and the break for drainage.  Then started around the North end of Building 'B'.





Friday 5/31/2013

Weather: Partly Cloudy 72˚/40˚   

Subs on Site
<Huskies>                        (3)
<Green Clean>                (2)
<Wall to Wall>                  (1)
<Reliance>                       (2)
<DG Concrete>                (3)

Work in Progress
(Huskies) Trenching and final grade around Building 'E'.

(Green Clean) Touched up Building 'D' and continued on Building 'E'.

(Wall to Wall) Touched up Building 'E'. 

(Reliance) Worked on the trim in the North tower of Building 'B' and items from Building 'E' final inspection.  

(DG Concrete) Graded the west side of Building 'B' for rock walls and the break for drainage. 

Big Dave (Deputy Fire Marshal) re inspected Building 'D' and 'E'.  We still did not have spare heads and a wrench in the riser room.  Extreme Fire will come Saturday and leave those items.  Dave will come back next week and pass it off. 



Thursday 5/30/2013

Weather: Partly Cloudy 71˚/40˚   

Subs on Site
<Huskies>                        (3)
<Green Clean>                (2)
<G&M Woods>                 (2)
<Wall to Wall>                  (1)
<Diamond Z>                    (3)
<Clegg Steel>                   (5)
<Air Doctors>                    (3)
<Reliance>                       (4)
<DG Concrete>                (3)

Work in Progress
(Huskies) Trenching and final grade around Building 'E'.

(Green Clean) Touched up Building 'D' and continued on Building 'E'.

(G&M) Finished counter tops on North tower of Building 'B'.  I called Melissa (SACO) and they are going to send a new above stove cabinet. 

(Wall to Wall) Prepped the breeze ways of Building 'D'. 

(Diamond Z) Caulked the column caps were they met with the steel.

(Clegg Steel) fixed the stairs in Building 'E', installed hand rails for the stairs in Building 'B',  cut down chimney caps, installed the sheets to cover the stair landings.

(Reliance) Worked on the trim in the North tower of Building 'B' and items from Building 'E' final inspection.  

(DG Concrete) Graded the west side of Building 'B' for rock walls and the break for drainage. 

We had final  re inspection on Building 'D'.  We pass for all but the exterior items and 2 notes for the plumber.  Aaron also asked that we install ramps at the end of the walks in the sections were we could not pour for safety.