Subs on Site
<Huskies> (5)
<Green Clean> (2)
<Wall to Wall> (4)
<SBS> (3)
<Reliance> (2)
<Elite Structures> (2)
<Red Oak> (5)
Work in Progress
(Huskies) Trenched around Building 'B' and the Club House.
(Green Clean) Rough clean of Building 'B'.
(Wall to Wall) Painted the body on the East side of Building 'E' exterior.
(SBS) Installed hardware and mirrors in Building 'B',
(Reliance) Trimed and tested Building 'B'.
(Elite Structures) Set their frames, painted and installed the covers. They left before they got the trim installed because Shane;s Dad had a heart attack.
(Red Oak) Installed 16 Kitchen sinks in the North Tower. Turned on water on to the North Tower. Their Bath tub trims did not come today. Ether completed the punch list for the other buildings and left for Agrium