Weather: Partly Cloudy / Windy 88˚/48˚
Subs on Site
(Green Clean) Touch up on Building 'D'. Started back on 'E'.
Subs on Site
<Precision Asphalt> (2)
<Huskies> (3)
<Green Clean> (2)
<Wall to Wall> (3)
<Wall to Wall> (3)
<SBS> (3)
<Cardalls> (2)
<Warburtons> (3)
<Clegg Steel> (6)
<Air Doctors> (2)
<Sterns> (6)
<Red Oak> (3)
<DG Concrete> (3)
Work in Progress
(Precision Asphalt) Striped around Buildings 'D' and 'E'. They started to lay out for Building 'B' stripes and discovered that the lot is 4 feet more narrow against the dumpster then at the entrance. Their stalls will not fit and meet code.
(Huskies) Started trenching around Building 'B'. Behind DG Concrete with sidewalk prep.
(Wall to Wall) Painted the trim on Building 'D'. Started caulking and touch up on C while the trim set up.
(SBS) Stocked the fridges in Building 'B', however the ranges and dishwashers did not come. Scott (Home Depot) could on track them down before end of business day..
(Cardalls) Blew in the insulation in Building 'B' then the Club House and met with Corey (IECC) inspector and touched up 'D' again.
(Warburtons) Installed the Rain gutters on B and C garages and touched up the fascia on A.
(Clegg Steel) Installed the cut down chimney caps and painted the PVC pipes on B, D, and E. and continued on Handrails in 'B'.
(Air Doctors) Installed the condensers for Building 'B'.
(Sterns) Poured sidewalk around 'E' and some in front of Building 'B'.
(Red Oak) Finished the last of Building 'E' inspection items under the inspectors nose then started installing their trim in Building 'B'.
(DG Concrete) Installed the road base under all of Building 'B' sidewalks.