Tuesday 6/12/2013

Weather: Sunny  89˚/53˚   

Subs on Site
<Huskies>                        (4)
<Green Clean>                (2)
<Wall to Wall>                  (4)
<SBS>                              (2)
<Reliance>                       (4)
<Elite Structures>             (2)
<Red Oak>                     (3)

Work in Progress
(Huskies) Trenched around Building 'B'.

(Green Clean)  Cleaned Building 'E'.  Started rough clean of Building 'B'.

(Wall to Wall) Caulked Building 'E' exterior.

(SBS) Installed hardware in Building 'B',  Started on Mirrors.

(Reliance) Trimed and tested Building 'B' and finished wiring for fire alarm.

(Elite Structures) Drilled for their footings at Building 'C', passed inspection, and poured them.

(Red Oak) Installed 16 Kitchen sinks in the South Tower.