Thursday 6/13/2013

Weather: Sunny  91˚/59˚   

Subs on Site
<Huskies>                        (5)
<Green Clean>                (2)
<Wall to Wall>                  (4)
<G&M Woods>                 (2)
<Reliance>                       (2)
<Red Oak>                     (2)

Work in Progress
(Huskies) Started final grade around Building 'B'.

(Green Clean)  Rough clean of Building 'B'.

(Wall to Wall) Painted the body on the South, West and North side of Building 'E' exterior.  Rob decided to repair the Back flow preventer that he hit with his lift. Rather than pay the $551 Huskies would charge.


(G&M Wood) Installed the counter tops in the Clubhouse and caulked the counter tops in 'B"

(Reliance) Trimed and tested Building 'B'.

(Red Oak)Install the last 16 kitchen sinks and started on the water heater drains

We had final inspection.  Aaron just noted that we were not ready and that all plumbing needed to be inspected again.