Subs on Site
<Precision Asphalt> (2)
<Huskies> (3)
<Green Clean> (2)
<Wall to Wall> (3)
<Wall to Wall> (3)
<Cardalls> (2)
<Warburtons> (3)
<Air Doctors> (2)
<Red Oak> (3)
<DG Concrete> (3)
Work in Progress
(Precision Asphalt) Laid out the strips around Buildings 'D' and 'E'.
(Huskies) Started trenching around Building 'B'.
(Wall to Wall) Tried to Paint the trim on Building 'D' but it was too windy. They Primed the Club House.
(Cardalls) Blew in the insulation in Building 'B' and met with Corey (IECC) inspector and touched up 'D' and 'E'.
(Warburtons) Installed the Rain gutters on Building 'C'.
(Air Doctors) Installed the condensers for Building 'B'.
(Red Oak) Stocked their trim in Building 'B'. Then started on the inspection list for Building 'E'. Standard did not have the clean out cover and Wynneilsons was close so they will finish in the morning.
(DG Concrete) Graded the west side of Building 'B' for rock walls and the break for drainage. Then started around the North end of Building 'B'.