Friday 5/31/2013

Weather: Partly Cloudy 72˚/40˚   

Subs on Site
<Huskies>                        (3)
<Green Clean>                (2)
<Wall to Wall>                  (1)
<Reliance>                       (2)
<DG Concrete>                (3)

Work in Progress
(Huskies) Trenching and final grade around Building 'E'.

(Green Clean) Touched up Building 'D' and continued on Building 'E'.

(Wall to Wall) Touched up Building 'E'. 

(Reliance) Worked on the trim in the North tower of Building 'B' and items from Building 'E' final inspection.  

(DG Concrete) Graded the west side of Building 'B' for rock walls and the break for drainage. 

Big Dave (Deputy Fire Marshal) re inspected Building 'D' and 'E'.  We still did not have spare heads and a wrench in the riser room.  Extreme Fire will come Saturday and leave those items.  Dave will come back next week and pass it off.