Subs on Site
<Huskies> (3)
<Green Clean> (2)
<Wholesale Flooring (4)
<Wall to Wall> (3)
<SBS> (1)
<Warburtons> (3)
<Reliance> (2)
<Air Doctors> (2)
<Red Oak> (3)
<DG Concrete> (3)
Work in Progress
(Huskies) Trenched around Building 'B'. Behind DG Concrete with sidewalk prep.
(Wholesale Flooring) Installed carpet in Building 'B' South Tower.
(Wall to Wall) Painted the remainder of the exterior body on Building 'D'. Stripped the masking and cleaned up.
(SBS) Installed hardware in Building 'B',
(Warburtons) Installed the Rain gutters on D.
(Reliance) Trimed and tested Building 'B' and started wiring the condensers.
(Air Doctors) Installed the condensers for Building 'B'. Installed the furnaces in the Club House
(Red Oak) Installing their trim in Building 'B'.




