Wednesday 6/5/2013

Weather: Partly Cloudy / 83˚/43˚   

Subs on Site
<Huskies>                        (3)
<Green Clean>                (2)
<Wholesale Flooring        (5)
<Wall to Wall>                  (3)
<SBS>                              (3)
<Warburtons>                  (6)
<Clegg Steel>                   (6)
<Air Doctors>                    (2)
<Red Oak>                       (3)
<DG Concrete>                (3)

Work in Progress
(Huskies) Trenched around Building 'B'.  Behind DG Concrete with sidewalk prep.

(Green Clean)  Cleaned Building 'E'.

(Wholesale Flooring) Installed the tack strip and delivered his carpet.

(Wall to Wall) Painted the body on Building 'D'.  Painted the Club House.

(SBS) Installed hardware in Building 'B',

(Warburtons) Installed the Rain gutters on D.  The siding guys worked on my punch list for Building 'B'.

(Clegg Steel) Installed the cut down chimney caps and painted the PVC pipes on A and C.

(Air Doctors) Installed the condensers for Building 'B'.

(Red Oak) Installing their trim in Building 'B'.  

(DG Concrete) Graded for the sidewalks in front of the Club House.