Friday 7/6/2012


Weather: Sunny 86˚/61˚


Subs on Site
<Red Oak>                                  (4)


Work in Progress:
(Red Oak) Pass inspection on Building 'C' garage footing and tied the bar for the slab on Southern half of Building 'A' until they ran out of #3 bar.  #3 bar was delivered this afternoon and the completed the bar and passed inspection.

I met with Mat (HUD) and went over the progress.  He interviewed Nate (Red Oak) who was the only one on site not interviewed.  Nick was called on the phone.

Thursday 7/5/2012


Weather: Sunny 88˚/61˚


Subs on Site
<Reliance>                                  (3)
<Red Oak Plumbing>                  (2)
<Red Oak>                                  (3)
<DG Concrete>                           (4)

Work in Progress:
 (Reliance) Organized their materials and trailer and worked with Cory(Legend) to layout their transformer locations.

(Red Oak Plumbing)hooked up to the water on the North end and set the tub boxes and floor drains on the whole building.

(Red Oak)Finished tieing the rebar for Building 'C' garage footings and started preping the slab on the Southern half of Building 'A'


(DG Concrete)graded the gravel for the slab on the Southern half of Building 'A'.




Wednesday 7/4/2012


Weather: Sunny 93˚/62˚


Subs on Site
<Reliance>                                  (3)
<Red Oak Plumbing>                  (2)
<Red Oak>                                  (3)
<DG Concrete>                           (4)

Work in Progress:
(Red Oak) helped (DG Concrete) layout the interior footings for the southern half of Building 'A'

(Red Oak Plumbing)back fill the portion of the north half of Building 'A' that passed inspection on Tuesday.  They were short on parts to complete and pressure test all of it.

Tuesday 7/3/2012


Weather: Sunny 94˚/59˚


Subs on Site
<Reliance>                                  (3)
<Red Oak Plumbing>                  (2)
<Red Oak>                                  (3)
<DG Concrete>                           (4)

Work in Progress:
(Reliance) set up the fax line to the Conex as well as temp power.

(Red Oak Plumbing) readied the underground on the north end of Building 'A' for inspection at the end of the day

(Red Oak) tied bar the the footings of Building 'C' garage.

(DC Concrete) laid more storm drain pipe and started digging Building 'D's footings

Monday 7/2/2012


Weather: Sunny 96˚/58˚


Subs on Site
<Reliance>                                  (3)
<Red Oak Plumbing>                  (6)
<Red Oak>                                  (3)
<DG Concrete>                           (4)

Work in Progress:
(Reliance) Started trenching for the temp power to the trailer and Building 'A'

(Red Oak Plumbing) readied the underground in the first half of Building 'A' for inspection, passed inspection, and back filled the trenches.

(Red Oak)formed the footing in Building 'C' garage footings so the could back fill them to allow accese all around for Building 'C'.

(DG Concrete) back filled the North end of Building 'A' slab, installed strom drain pipe and pressure tested the sewer line from Main St to our first manhole.

Friday 6/29/2012

Weather: Sunny 97˚/62˚


Subs on Site
<RAM>                                       (2)
<Red Oak Plumbing>                  (1)
<Red Oak>                                  (7)

Work in Progress:
(RAM) Unloaded another load of lumber and continued to organize there Lumber Lot.

(Red Oak Plumbing)dug their first trenches and committed to inspection on Monday AM for the first half of Building 'A' underground.  It was decided that we will go ahead with Type 'B' units all the way up instead of the standard unit floor plan.


(Red Oak Concrete) pour the North Breeze way walls and the outer columns on the whole of Building 'A'.

Thursday 6/28/2012


 Weather: Sunny & Windy 94˚/59˚

Subs on Site
<RAM>                                       (2)
<Red Oak Plumbing>             (1)
<Red Oak>                                (7)
<DG Concrete>                         (4)

Work in Progress:
(RAM) Continued to arrange their lumber stacks and started installing their temp fence.  They gave me  the a key to the conex and fence.

(Red Oak) stripped the forms on the north end of Building 'A' and finished forming the north breeze way walls.  The inspection was schedule for Noon, I called at 1:00 and they had scheduled it for tomorrow.  This is the second time they have done this.  Mat (Inspector) came by around 3:00 and pass us.  We rescheduled the mud for 9:30 am tomorrow.


(DG Concrete) Conpacted the E-fill lift on the interior footings on the south end of Building 'A' and backed filled the interior to middle of Building 'A'.  They also started prepping the footings on Building 'D' &'E'.















Wednesday 6/27/2012

 Weather: Sunny & Windy 95˚/59˚


Subs on Site
<RAM>                                       (4)
<Red Oak Plumbing>             (1)
<Red Oak>                                (7)
<DG Concrete>                         (4)
<Horrocks>                               (1)

Work in Progress:
(RAM) started to set up their staging area and delivered a brand new forklift.

(Red Oak Plumbing) delivered a mini-ex on site.

(Red Oak Concrete) Finished forming the north section tall walls, passed inspection, and poured. I was told the pour would be at 2:00 PM and it did not start until 3:15.  Ron (Horrocks) had to wait. Then started forming the north breeze way walls.

(DG Concrete) Fixed the hydrant and poured a large thrust block behind it.  They passed inspection on Building 'C' garage footings and failed on Building  'B' garage footings.  Shad (DG Concrete) backfilled the southern end of Building 'A'.  Chris (DG Concrete) set all of the storm drain boxes.



Tuesday 6/26/2012


Weather Sunny & Windy 96˚/60˚


Subs on Site
<Red Oak>            (7)
<DG Concrete>      (4)

Work in Progress:
Wayne (Extreme Fire) met with Jeremy and Ryan (Fire Marshall) and conducted a flow test on the fire hydrants.



(Red Oak) Stripped forms South Breezeway walls and the East side of middle section.  Started tieing bar and forming for the north section.


(DG Concrete) Re-Compacted the footings on Building 'C' garage. Finished digging and filling footings on Building 'B' garage.  Chris (DG Concrete) Fire lane prep.  Jesse (DG Concrete) Backed off a 3 foot cliff with the water truck,  Chris (DG Concrete) told him he has to be aware of everything around him while operating equipment.  15 seconds later Jesse (DG Concrete) hit the fire hydrant.  Brandon (Maeser) came to collect a sample for the 2nd of 2 bacterial cultures on our water line.










Monday 6/25/2012


Weather Sunny & Windy 96˚/54˚


Subs on Site
<Red Oak>            (7)
<DG Concrete>      (4)
<Horrocks>            (1)

Work in Progress:
(Red Oak) Finished forming South Breezeway walls and the East side of middle section.  Inspected and poured.

(DG Concrete) Re-Compacted the footings on Building 'C' garage.  Compaction passed on all but one corner.  Started digging a filling footings on Building 'B' garage.  Chris (DG Concrete) started on fire lane prep.  (DG Concrete) added 3 yrds of concrete to (Red Oak's) pour for trust blocks.

I was unloading lumber until after 8 PM.