Weather Sunny & Windy 96˚/54˚
Subs on Site
<Red Oak> (7)
<DG Concrete> (4)
<Horrocks> (1)
Work in Progress:


(DG Concrete) Re-Compacted the footings on Building 'C' garage. Compaction passed on all but one corner. Started digging a filling footings on Building 'B' garage. Chris (DG Concrete) started on fire lane prep. (DG Concrete) added 3 yrds of concrete to (Red Oak's) pour for trust blocks.
I was unloading lumber until after 8 PM.