Friday 6/29/2012

Weather: Sunny 97˚/62˚


Subs on Site
<RAM>                                       (2)
<Red Oak Plumbing>                  (1)
<Red Oak>                                  (7)

Work in Progress:
(RAM) Unloaded another load of lumber and continued to organize there Lumber Lot.

(Red Oak Plumbing)dug their first trenches and committed to inspection on Monday AM for the first half of Building 'A' underground.  It was decided that we will go ahead with Type 'B' units all the way up instead of the standard unit floor plan.


(Red Oak Concrete) pour the North Breeze way walls and the outer columns on the whole of Building 'A'.