Wednesday 6/27/2012

 Weather: Sunny & Windy 95˚/59˚


Subs on Site
<RAM>                                       (4)
<Red Oak Plumbing>             (1)
<Red Oak>                                (7)
<DG Concrete>                         (4)
<Horrocks>                               (1)

Work in Progress:
(RAM) started to set up their staging area and delivered a brand new forklift.

(Red Oak Plumbing) delivered a mini-ex on site.

(Red Oak Concrete) Finished forming the north section tall walls, passed inspection, and poured. I was told the pour would be at 2:00 PM and it did not start until 3:15.  Ron (Horrocks) had to wait. Then started forming the north breeze way walls.

(DG Concrete) Fixed the hydrant and poured a large thrust block behind it.  They passed inspection on Building 'C' garage footings and failed on Building  'B' garage footings.  Shad (DG Concrete) backfilled the southern end of Building 'A'.  Chris (DG Concrete) set all of the storm drain boxes.