Thursday 6/28/2012


 Weather: Sunny & Windy 94˚/59˚

Subs on Site
<RAM>                                       (2)
<Red Oak Plumbing>             (1)
<Red Oak>                                (7)
<DG Concrete>                         (4)

Work in Progress:
(RAM) Continued to arrange their lumber stacks and started installing their temp fence.  They gave me  the a key to the conex and fence.

(Red Oak) stripped the forms on the north end of Building 'A' and finished forming the north breeze way walls.  The inspection was schedule for Noon, I called at 1:00 and they had scheduled it for tomorrow.  This is the second time they have done this.  Mat (Inspector) came by around 3:00 and pass us.  We rescheduled the mud for 9:30 am tomorrow.


(DG Concrete) Conpacted the E-fill lift on the interior footings on the south end of Building 'A' and backed filled the interior to middle of Building 'A'.  They also started prepping the footings on Building 'D' &'E'.