Weather: Sunny & Windy 94˚/59˚
Subs on Site
<RAM> (2)
<Red Oak> (7)
<DG Concrete> (4)
Work in Progress:
(RAM) Continued to arrange their lumber stacks and started installing their temp fence. They gave me the a key to the conex and fence.

(DG Concrete) Conpacted the E-fill lift on the interior footings on the south end of Building 'A' and backed filled the interior to middle of Building 'A'. They also started prepping the footings on Building 'D' &'E'.