Friday 7/20/2012


Weather: Partly Cloudy 94˚/67˚


Subs on Site
<TouchStone>                              (6)
<Reliance>                                   (3)
<Red Oak>                                  (8)
<Horrocks>                                  (1)
<Legend>                                     (1)

Work in Progress:
(Touchstone) finished chalking the lines on first half of Building 'A'.  They needed dimensions for the bathroom and kitchen in a couple of the unit pages.  We also discovered a couple of places were the plumbing missed the walls.  First was in the laundry room of the 3x2 Type 'A' unit and the other was the kitchen sink in the same unit.

(Reliance) Trenched on the primary's for the site power.  They hit and bent  a water valve cover for building 'C'.

(Red Oak) set up one side of the Western end of Building 'C'.

(Horrocks) tested the compaction the the worst part of the road just South East of the intersection and it came up at 93%+ on the first 8".

(Legend) came on site to shot the light poles on the East end of the site.





500 South (Questar)

500 South


Thursday 7/19/2012


Weather: Partly Cloudy 93˚/62˚


Subs on Site
<TouchStone>                              (6)
<Reliance>                                   (3)
<Red Oak>                                  (8)
<Horrocks>                                  (1)
<DG Concrete>                            (4)

 Work in Progress:
(TouchStone) set up their camp and started chalking lines and stocking lumber for Building 'A'

(Reliance) poured six light posts on West side of Building 'A' and hooked up temp power for Ram Builders 3 trailers.

(Red Oak) stripped the forms and started forming Building 'D' footing, The walls on Building 'C' and the center shear walls for Building 'C's garage.

(DG Concrete) finished rough grade and curb and gutter on Building 'A' parking lot.  The also dug the first half of Building 'B' footings and pass compaction  1/4 of it.



Wednesday 7/18/2012


Weather: Partly Cloudy 92˚/58˚


Subs on Site
<Reliance>                                   (3)
<Red Oak>                                  (8)
<Horrocks>                                  (1)
<DG Concrete>                            (4)

Work in Progress:
(Reliance) poured six light poles and prepped to pour six more tomorrow.

(Red Oak)Poured the footings for Building 'C' and the stem walls for 'C's garage.  Then started laying out Building 'D' footings.

(DG Concrete) cut in the curb around Building 'A' and started adding E fill under it.  They passed compaction on Building 'E' and started digging Building 'B'.






Change of elevation.
 There will be a 4.75 foot wall on the building footings
 

Tuesday 7/17/2012



Weather: Partly Cloudy 86˚/57˚


Subs on Site


<Reliance>                                   (2)
<Red Oak>                                  (8)
<Horrocks>                                  (1)
<DG Concrete>                            (4)
<Legend>                                     (2)

Work in Progress:

(Reliance) continued to back fill the trench by Building 'C'.  We laid out the light poles around Building 'A' with the surveyor and discovered that the pole at the North East entrance was against the gable.  We moved the pole over a few feet to line up with the South side of the patio yet still out of the rock walls.

(Red Oak) finished forming the footings for Building 'C' and the foundation walls on Building 'C' garage.  Passed inspection on both.


(DG Concrete) Finished digging Building 'E' footings, touched up the grade on Building 'D', and started grading for curb on around Building 'A'.

(Legend) arrived on site a 10:00 AM and started with the light poles and curb around Building 'A' and the four corners of Building 'B's parking lot.  Lonny (Legend) noticed some flow issues with the curb elevations.

The North West section of Building 'A' had a fall of 1' across the sidewalk.  He raised the grade to match better across the sidewalk.
The Southern approach had a 15% grade coming into the lot. He raised the corners of the approach by a foot and in tapered into the other grades just fine.
The flow of water from the approach to the garage was steep enough to require a curb against the garage wall.  He requested that we add the curb on the West end wall of the garage.

Monday 7/16/2012


Weather: Partly Cloudy 85˚/56˚

Subs on Site

< Bandwidth>                               (2)
<Reliance>                                   (2)
<Red Oak>                                  (8)
<Horrocks>                                  (1)
<DG Concrete>                            (4)

Work in Progress:
(Strata) & (Reliance) Started trenching on the south end of Building 'A' and worked their way up to Building 'C' and out to 2500 W.  Passed inspection and back filled.

(Red Oak) formed and tied bar in Building 'C's footings.  They also worked a part day on Saturday until the rain came.

(DG Concrete) Dug and compacted Building 'E' footings, passed compaction on Building 'D', and continued the fire lane fabric and sub-grade from the Club house intersection to the southern project boundary.  Then compacted the fire lane sub grade,


Dennis (Sterns) stopped by the site and we went over the phasing and schedule.











Building 'C'
From 2500 W

Friday 7/13/2012


Weather: Partly Cloudy 93˚/59˚

Subs on Site

<Reliance>                                   (2)
<Red Oak>                                  (6)

Work in Progress:
I met with Bill (Utah Landscape) we discussed the irrigation plan.   Bill (Utah Landscape) had a couple concerns first was the island in Building 'A's parking lot, the plans show grass and trees and access for irrigation would be hard.  The other concern was, the plan calls for 3' of mulch surrounding each building.    Bill (Utah Landscape) Thinks that will not look very good.



(Red Oak) worked on Building 'C's footings.






500 S progress


(500 South  progress )
We  will be adding utility stubs soon

Thursday 7/12/2012





Weather: Partly Cloudy 94˚/61˚

Subs on Site

<Reliance>                                   (2)
<Red Oak>                                  (8)
<Horrocks>                                  (1)
<DG Concrete>                            (4)



Work in Progress:

(Red Oak) Pour the center section of Building 'A' at 4 AM and the breeze ways and patios at 4 PM.

(DG Concrete) compacted all of Building 'D's footings and started digging Building 'E'.  Chris and Tim (DG Concrete) installed the fabric and 8" of sub base for the fire road from 2500 W to the intersection in front of the Club house.

(Reliance) sleeved the road from Building 'D'&'E' to Building 'B' before the road was installed.

Ben (Horrocks) preformed the concrete tests and compaction on Building 'D' the out side walls failed



Wednesday 7/11/2012


 Weather: Sunny 95˚/65˚


Subs on Site

<Reliance>                                   (2)
<Red Oak>                                  (8)
<Horrocks>                                  (1)
<DG Concrete>                            (5)


Work in Progress:

(Reliance) poured the light poles on the North side of the main road and trenched the conduit between them.

(Red Oak) formed more footings on Building 'C' and poured the North end of Building 'A'

(DG Concrete) dug the remainder of Pond #2 note the standing water in the low end.  Dug Building 'C's footings and added E fill.  They also started on the fabric and the Fire Lane towards the end of the day.







Tuesday 7/10/2012

 Weather: Sunny 95˚/65˚


Subs on Site
<Reliance>                                   (2)
<Red Oak>                                  (8)
<Horrocks>                                  (1)
<Legend>                                     (1)
<DG Concrete>                            (5)

Work in Progress:
(Reliance) dug the light posts on the North side of the road and discovered that one of them landed right on where we had placed a water meter for Building 'B'.

(Red Oak) tied the last of the bar for Building 'A' slab, passed inspection, and poured one end of the Buildings slab.


Cory (Legend) laid out the light pole locations on the  North side of the street for Reliance and then gave Chris (DG Concrete) stakes for the second pond.

(DG Concrete) graded down the breeze ways for our 2" step into the units and added gravel for the patios on Building 'A'.  They also added dirt on the west side of Building 'A' for the parking lot.  Chris(DG Concrete) started digging the second pond.


Monday 7/9/2012


 Weather: Sunny 93˚/60˚


Subs on Site
<Reliance>                                   (3)
<Red Oak>                                  (7)
<Horrocks>                                  (1)
<DG Concrete>                            (5)

Work in Progress:
(Reliance)hooked up the temporary power to the trailer as well as their trailer.  Bryson (Reliance) met
with Mike (Bandwidth) and me about Bandwidth's low voltage requirements.

(Red Oak) laid out the footings for Building 'C' and started forming until the second half of Building 'A's slab was graded, then they tied the bar on the North end, in prep for the inspection and pour tomorrow.

(DG Concrete) cut the rest of the east parking lot for  Building 'A' down to sub grade and grouted the storm drain pipes.