Subs on Site
<TouchStone> (6)
<Reliance> (3)
<Red Oak> (8)
<Horrocks> (1)
<Legend> (1)
Work in Progress:

(Reliance) Trenched on the primary's for the site power. They hit and bent a water valve cover for building 'C'.
(Red Oak) set up one side of the Western end of Building 'C'.
(Horrocks) tested the compaction the the worst part of the road just South East of the intersection and it came up at 93%+ on the first 8".
(Legend) came on site to shot the light poles on the East end of the site.

![]() |
500 South (Questar) |
![]() | |
|