Friday 7/20/2012


Weather: Partly Cloudy 94˚/67˚


Subs on Site
<TouchStone>                              (6)
<Reliance>                                   (3)
<Red Oak>                                  (8)
<Horrocks>                                  (1)
<Legend>                                     (1)

Work in Progress:
(Touchstone) finished chalking the lines on first half of Building 'A'.  They needed dimensions for the bathroom and kitchen in a couple of the unit pages.  We also discovered a couple of places were the plumbing missed the walls.  First was in the laundry room of the 3x2 Type 'A' unit and the other was the kitchen sink in the same unit.

(Reliance) Trenched on the primary's for the site power.  They hit and bent  a water valve cover for building 'C'.

(Red Oak) set up one side of the Western end of Building 'C'.

(Horrocks) tested the compaction the the worst part of the road just South East of the intersection and it came up at 93%+ on the first 8".

(Legend) came on site to shot the light poles on the East end of the site.





500 South (Questar)

500 South