Subs on Site
<Reliance> (3)
<Red Oak> (8)
<Horrocks> (1)
<DG Concrete> (4)
Work in Progress:
(Reliance) poured six light poles and prepped to pour six more tomorrow.
(Red Oak)Poured the footings for Building 'C' and the stem walls for 'C's garage. Then started laying out Building 'D' footings.


![]() |
Change of elevation. There will be a 4.75 foot wall on the building footings |