Wednesday 7/18/2012


Weather: Partly Cloudy 92˚/58˚


Subs on Site
<Reliance>                                   (3)
<Red Oak>                                  (8)
<Horrocks>                                  (1)
<DG Concrete>                            (4)

Work in Progress:
(Reliance) poured six light poles and prepped to pour six more tomorrow.

(Red Oak)Poured the footings for Building 'C' and the stem walls for 'C's garage.  Then started laying out Building 'D' footings.

(DG Concrete) cut in the curb around Building 'A' and started adding E fill under it.  They passed compaction on Building 'E' and started digging Building 'B'.






Change of elevation.
 There will be a 4.75 foot wall on the building footings