Tuesday 7/17/2012



Weather: Partly Cloudy 86˚/57˚


Subs on Site


<Reliance>                                   (2)
<Red Oak>                                  (8)
<Horrocks>                                  (1)
<DG Concrete>                            (4)
<Legend>                                     (2)

Work in Progress:

(Reliance) continued to back fill the trench by Building 'C'.  We laid out the light poles around Building 'A' with the surveyor and discovered that the pole at the North East entrance was against the gable.  We moved the pole over a few feet to line up with the South side of the patio yet still out of the rock walls.

(Red Oak) finished forming the footings for Building 'C' and the foundation walls on Building 'C' garage.  Passed inspection on both.


(DG Concrete) Finished digging Building 'E' footings, touched up the grade on Building 'D', and started grading for curb on around Building 'A'.

(Legend) arrived on site a 10:00 AM and started with the light poles and curb around Building 'A' and the four corners of Building 'B's parking lot.  Lonny (Legend) noticed some flow issues with the curb elevations.

The North West section of Building 'A' had a fall of 1' across the sidewalk.  He raised the grade to match better across the sidewalk.
The Southern approach had a 15% grade coming into the lot. He raised the corners of the approach by a foot and in tapered into the other grades just fine.
The flow of water from the approach to the garage was steep enough to require a curb against the garage wall.  He requested that we add the curb on the West end wall of the garage.