Monday 7/16/2012


Weather: Partly Cloudy 85˚/56˚

Subs on Site

< Bandwidth>                               (2)
<Reliance>                                   (2)
<Red Oak>                                  (8)
<Horrocks>                                  (1)
<DG Concrete>                            (4)

Work in Progress:
(Strata) & (Reliance) Started trenching on the south end of Building 'A' and worked their way up to Building 'C' and out to 2500 W.  Passed inspection and back filled.

(Red Oak) formed and tied bar in Building 'C's footings.  They also worked a part day on Saturday until the rain came.

(DG Concrete) Dug and compacted Building 'E' footings, passed compaction on Building 'D', and continued the fire lane fabric and sub-grade from the Club house intersection to the southern project boundary.  Then compacted the fire lane sub grade,


Dennis (Sterns) stopped by the site and we went over the phasing and schedule.











Building 'C'
From 2500 W