
Subs on Site
< Bandwidth> (2)
<Reliance> (2)
<Red Oak> (8)
<Horrocks> (1)
<DG Concrete> (4)
Work in Progress:
(Strata) & (Reliance) Started trenching on the south end of Building 'A' and worked their way up to Building 'C' and out to 2500 W. Passed inspection and back filled.

(DG Concrete) Dug and compacted Building 'E' footings, passed compaction on Building 'D', and continued the fire lane fabric and sub-grade from the Club house intersection to the southern project boundary. Then compacted the fire lane sub grade,
Dennis (Sterns) stopped by the site and we went over the phasing and schedule.

![]() |
Building 'C' |
![]() |
From 2500 W |