Subs on Site
<TouchStone> (6)
<Reliance> (3)
<Red Oak> (8)
<Horrocks> (1)
<DG Concrete> (4)
Work in Progress:
(TouchStone) set up their camp and started chalking lines and stocking lumber for Building 'A'
(Reliance) poured six light posts on West side of Building 'A' and hooked up temp power for Ram Builders 3 trailers.
(Red Oak) stripped the forms and started forming Building 'D' footing, The walls on Building 'C' and the center shear walls for Building 'C's garage.
(DG Concrete) finished rough grade and curb and gutter on Building 'A' parking lot. The also dug the first half of Building 'B' footings and pass compaction 1/4 of it.