Tuesday 11/13/2012


Weather: Sunny 45˚/22˚

Subs on Site
<Warburtons>               (4)
<Standard Builders>     (3)
<Diamond Z>                 (5)
<Air Doctors>                (3)
<Reliance>                    (6)
<Utek>                          (21)
<Red Oak Plumbing>     (7)
<DG Concrete>             (2)

Work in Progress:
(Inspections) Aaron (Uintah County) inspected and passed 2 of the 8 units on 1st floor of Building 'A'
as well as passing 7 of the 16 gas lines on the North end of Building 'A'

(Warburtons)  worked on drying in Building 'C' garage. Stocked the material for Building 'A' roof.  Started drying in Building 'A'

(Standard Builders)Set the metal door frames we had to make up to 1/4" notches in the trimmers for a few of the doors to fit.

(Diamond Z) wrapped their tar paper and lath around Building 'A'

(Air Doctors) finished odds and ends with their line set including repairing the damage by other subs.  They also worked on dryer boxes and exhaust vents on the top floor.

(Reliance) ran the 1 1/4" smurf tube for Strata and boxed 2nd floor units.

(Utek) framed the closets under the stairs for Building 'A'.  Installed draft stops on Building 'D' & 'E'.  Started setting sections of Building 'C' 3rd floor.

(DG Concrete) Built rock walls on the West side of Building 'A'.  A neighbor came by and ask us to scrape the gravel off the road in front of their house.  Shad (DG Concrete) did so.




Monday 11/12/2012


Weather: Sunny 38˚/19˚

Subs on Site
<Warburtons>               (3)
<Standard Builders>     (3)
<Diamond Z>                 (2)
<Air Doctors>                (3)
<Reliance>                    (6)
<Utek>                          (17)
<Red Oak Plumbing>     (4)
<DG Concrete>             (2)

Work in Progress:
(Warburtons) started drying in Building 'C' garage.

(Standard Builders) Delivered their camper trailer. Spread out all the metal door frames for Building 'A'. The first door they set was framed 1/4" smaller than their rough opening should have been.  Joe (Standard Builders) express concern about setting the doors if all of them are too small.   We talked with Alma (Utek) if any of the doors will not fit Alma will make the adjustments.

(Diamond Z) went over the layout of the stone and got ready to dry in tomorrow.  Jesse says that the side walls of the patios were excluded from his bid

(Air Doctors) finished the fire caulking including adding caulk on the floor side of the flue penetrations.

(Reliance) swept out the 1st floor, finished fire caulking, and boxed on the 2nd floor.

(Utek) finished straps on the exterior of Building 'E'.  Continued the pre fab of Building 'C' 3rd Floor.  Built the wood columns around the entry gables for Building 'A'.

(DG Concrete) worked on the rock walls on the North West corner of Building 'A'  

Sub Meeting:
11/12/2012-

Bryson (Reliance)
Jesse (Diamond Z)
Jesse (Utek)
Alma (Utek)
Shad (DG Concrete)
William (Air Doctors) late

Pre-Rock inspection schedule (We will be insulating the whole unit after this inspection)-

  1. 1st floor   11/13/2012
  2. 2nd floor  11/15/2012  
  3. 3rd floor   11/20/2012
  4. 4th floor   11/27/2012
The inspector is focused on the fire caulking and draft stops.  Any holes through the party walls will have to covered/filled.  Any penetrations between units IE through party walls or ceilings need to be fire caulked on both sides.

The lower stairs for Building 'C', 'D', and 'E' will be here 11/19.

The stone will have the scratch coat on by the end of the week.  We discussed the siding starting and focusing on the East center section. So that the ground can be flat until they finish.  The stone will follow behind the excavators rock walls.

William (Air Doctors)said he should have more guys when we start ducting the floors and that their production should be 2-3 units/day.





Friday 11/9/2012

Weather: Rain/Snow 58˚/39˚

Subs on Site
<LKL>                           (5)
<Reliance>                    (6)
<Utek>                          (22)
<Red Oak Plumbing>     (7)

Work in Progress:
I was not on site.  The remaining sheet rock was stocked and covered.  Building 'E' wall were completed.

Thursday 11/8/2012

Weather: Sunny 61˚/30˚

Subs on Site
<LKL>                           (5)
<Reliance>                    (6)
<Utek>                          (22)
<Red Oak Plumbing>     (7)
<DG Concrete>             (2)

Work in Progress:
(LKL) Stocked almost 75% of Building 'A' drywall.  They worked until at least 7:00 pm and covered the entire 4th floor stacks with Visqueen as well as tarped all drywall left out side.  I spoke with Caleb (LKL) as well as the stockers 3 or 4 times about covering the drywall well.  They will bring enough Visqueen to cover every stack tomorrow. 

(Reliance)finished pulling wire in all of Building 'A' 1st floor units and started make up
             Bryson (Reliance) met with Rodney Bell (Strata) to discuss low voltage.  Reliance will send me report of what they decided.

(Utek) Finished the 2nd floor walls on Building 'D'.  Started 2nd floor walls on Building 'E' finishing one unit.  Worked on prefab for Building 'C' 3rd floor.  Hung 75% of the Windows on Building 'A'.
(Red Oak Plumbing) worked on the Gas lines and Water Supply lines for 1st and 2nd floors of Building 'A'

(DG Concrete) Built rock walls on the North end of Building 'A' and the first Window Well for the patios on the North end of the West side.

(CR Doors)delivered all but 4 of the HM Door frames.



Sub Meeting:
Randy (Warburtons) and Shad (DG Concrete) discussed leaving the West center section level for the frist week of Siding so that Warburtons can side that section before rock wall make access harder.  I spoke with Caleb King (LKL) to make sure that all drywall is securely covered before the storm comes in tomorrow morning.







Wednesday 11/7/2012

Weather: Sunny 61˚/30˚

Subs on Site
<Reliance>                    (6)
<Utek>                          (22)
<Red Oak Plumbing>     (7)
<DG Concrete>             (2)

Work in Progress:
(Reliance) pulled wire in nearly all of Building 'A' 1st floor units.

(Utek) Built and installed 2 of the 4 chimneys and 2 of the 4 entry gables.  They moved the crane to Building 'C'.  Built 3 of the 4 units for Building 'D' 2nd floor.  Pre Fabbed the 3rd floor for Building 'C'.

(Red Oak Plumbing) installed the tubs in Building 'A' except for the ADA units and ran the gas lines for the North end 1st and 2nd floors in Building 'A'.

(DG Concrete) installed the rock wall on the NE corner of Building 'A' they built it according to plan until I reminded them that all of the elevations have changed and we need to design build all rock walls.




Tuesday 11/6/2012

Weather: Sunny 57˚/35˚

Subs on Site
<Nutek>                         (3)
<Reliance>                    (6)
<Utek>                          (22)
<Red Oak Plumbing>     (7)
<DG Concrete>             (4)

Work in Progress:
(Nutek) drywall behind the tubs and flue chases on the 3rd and 4th floors of Building 'A'


(Reliance) boxed and drilled out Building 'A' 1st floor 

(Utek) framed the North end of the roof and sheeted it.  Finished all the pick-up on the South end of Building 'A'.  Started on the chimneys.

(Red Oak Plumbing) ran the gas pipe on the North end of the 1st floor of Building 'A'.  Set the tubs on the 2nd floor. Ran water main lines on the 1st floor. 

(DG Concrete)Built the rock walls around Building 'C' cleaned all in-road valve boxes and the key works on them all!



Sub Meeting:
Ether (Red Oak)
Bryson (Reliance)
Paul (Utek)
Shad (DG Concrete)

We discussed safety around the building.  The breeze ways are the safe zones for entry and inside the curb is a drop zone.  Utek will finish the West side today so that DG concrete can start building rock walls.  The schedule is to have our preliminary 4-way tomorrow so that we can get a feel for what the County will be looking at on the interior and we can pass the structural and start stone.  I told them we will be stocking the drywall on Friday and Saturday and they said could work around that.  The actual 4-way will be on Tuesday 11/13 because Monday 11/12 is a holiday.  Ether will finish all the plumbing and Bryson will finish the first floor in building 'A' by the 10th.  Bryson will finish pulling wire on the next floors every 3 days from there on out.  Bryson asked about eliminating the siding under the stairs so they could just attach the low voltage directly to the sheeting.  i asked Ether to replace the studs they had to remove to install the tubs he agreed.

I also met with Randy Deets (RMP) he told me they would be out tomorrow and should have the power for Building 'A'.  

Jeremey (Fire Marshall) came and passed off the the 1st and 2nd floor with a couple of add on notes.  We need to add sprinklers in the under stair closets.  There was also a spot were the gas line pushed the sprinkler pipe out of plumb.  I spoke with Ether and he said he would move the gas line over just a bit.

Monday 11/5/2012

 Weather: Sunny 60˚/30˚

Subs on Site
<Reliance>                    (5)
<Utek>                          (22)
<Red Oak Plumbing>     (5)
<DG Concrete>             (4)

Work in Progress:
(Reliance) Made up the panels on Building 'A' and drilled out.

(Utek)focused on Building 'A' portions of Less, Jesse, and Hyrum's crew joined in with Alma's crew and worked on the roof finishing the overbuilds and sheeting 1/2 of the South end.  Jesse took all of the framers not on the roof and worked on pick up for the North end interior.

(Red Oak Plumbing) drilled out the South end of 1st floor for Building 'A' for gas lines and main water lines.
 

(DG Concrete) continued on rock walls and sidewalks on the North side of Building 'C'.  We ran into trouble trying to fit window wells and the condensers in the center section. 

Friday 11/2/2012


 Weather: Sunny 61˚/36˚

Subs on Site
<RMP>                         (4)
<Diamond Z>                (6)
<Reliance>                    (5)
<Utek>                          (22)
<Red Oak Plumbing>     (5)

Work in Progress:
(Diamond Z) laid the brick for 4 1/2 of the 5 dumpster enclosures .

(Reliance) worked on panels and drilling out Building 'A'  1st floor.

(Utek)Framed the last unit on Building 'C' 2nd Floor and buttoned up the sheer.  Rolled the 2nd floor on Building 'E'. Sheeted Saturday.  Set all of the gables on the steel columns for Building 'A'.

(Red Oak Plumbing)ran the vent pipes for the rest of Building 'A'.

Pavement cracks sealed

Thursday 11/1/2012


 Weather: Sunny 63˚/36˚

Subs on Site
<Extreme Fire>             (3)
<Reliance>                    (5)
<Utek>                          (22)
<Red Oak>                    (6)
<Red Oak Plumbing>     (5)
<DG Concrete>             (2)

Work in Progress:
(Extreme Fire) finished the South end of Building 'A'

(Reliance)pull the last of the services to Building 'A' and pull the mule wire in for RMP

(Utek)Sheeted the rest of the main section of Building 'A' roof, started the overbuilds, set 10 of the 16 steel columns, set all but 1 1/2 units on Building 'C' 2nd floor walls, Sheeted the 2nd floor on Building 'D' and continued pre-Fab

(Red Oak) poured the corridors and decks on the North end of Building 'A' 
(Red Oak Plumbing) drilled the 3rd and 4th floors for drains and vents 

(DG Concrete) set rock walls on the North East corner of Building 'C' as well as flattened out the area for Utek's crane.

Windows were delivered on site for Building 'A'

Sub Meeting:
I met with Jesse (Diamond Z Stone) we discussed the stone caps on the chimney and angled columns.  Jesse asked if the chimney and or chimney cap could be smaller than what the plans showed.  We decided that we had better just stick with the plans so there would be no problems with framing or steel.  Although, we are going to slope the caps to keep water out of the chimney.
We also looked though the plans for anything that called out a sill on top of the windows and could not find anything.

Wednesday 10/31/2012

Weather: Sunny 64˚/32˚

Subs on Site
<Clegg Steel>               (1)
<Extreme Fire>             (3)
<Reliance>                    (4)
<Utek>                          (19)
<Red Oak>                    (8)
<Red Oak Plumbing>     (6)
<DG Concrete>             (2)

Work in Progress:
(Clegg Steel) Sent a man up with the embeds for the dumpster gates and to cut down the base plates

(Extreme Fire) worked on the North end units on 3rd and 4th floor.

(Reliance) pulled feeders to the panels on the top floors 

(Utek) sheeted the roof of building 'A', set 2 of 16 steel columns for the upper trusses, stood 2 1/2 units on Building 'C' second floor, rolled the 2nd floor on Building 'D', and worked on pre-fab.

(Red Oak)Poured the corridors and decks on the South end of Building 'A'


(Red Oak Plumbing) worked on the vents and drains for Building 'A' 2nd floor and started drilling for the gas mains on 1st floor.

(DG Concrete) Backfilled around Building 'A' then started rock walls behind Building 'C'