Wednesday 11/7/2012

Weather: Sunny 61˚/30˚

Subs on Site
<Reliance>                    (6)
<Utek>                          (22)
<Red Oak Plumbing>     (7)
<DG Concrete>             (2)

Work in Progress:
(Reliance) pulled wire in nearly all of Building 'A' 1st floor units.

(Utek) Built and installed 2 of the 4 chimneys and 2 of the 4 entry gables.  They moved the crane to Building 'C'.  Built 3 of the 4 units for Building 'D' 2nd floor.  Pre Fabbed the 3rd floor for Building 'C'.

(Red Oak Plumbing) installed the tubs in Building 'A' except for the ADA units and ran the gas lines for the North end 1st and 2nd floors in Building 'A'.

(DG Concrete) installed the rock wall on the NE corner of Building 'A' they built it according to plan until I reminded them that all of the elevations have changed and we need to design build all rock walls.