Subs on Site
<Reliance> (6)
<Utek> (22)
<Red Oak Plumbing> (7)
<DG Concrete> (2)
Work in Progress:
(Reliance) pulled wire in nearly all of Building 'A' 1st floor units.
(Utek) Built and installed 2 of the 4 chimneys and 2 of the 4 entry gables. They moved the crane to Building 'C'. Built 3 of the 4 units for Building 'D' 2nd floor. Pre Fabbed the 3rd floor for Building 'C'.

(DG Concrete) installed the rock wall on the NE corner of Building 'A' they built it according to plan until I reminded them that all of the elevations have changed and we need to design build all rock walls.