Thursday 11/1/2012


 Weather: Sunny 63˚/36˚

Subs on Site
<Extreme Fire>             (3)
<Reliance>                    (5)
<Utek>                          (22)
<Red Oak>                    (6)
<Red Oak Plumbing>     (5)
<DG Concrete>             (2)

Work in Progress:
(Extreme Fire) finished the South end of Building 'A'

(Reliance)pull the last of the services to Building 'A' and pull the mule wire in for RMP

(Utek)Sheeted the rest of the main section of Building 'A' roof, started the overbuilds, set 10 of the 16 steel columns, set all but 1 1/2 units on Building 'C' 2nd floor walls, Sheeted the 2nd floor on Building 'D' and continued pre-Fab

(Red Oak) poured the corridors and decks on the North end of Building 'A' 
(Red Oak Plumbing) drilled the 3rd and 4th floors for drains and vents 

(DG Concrete) set rock walls on the North East corner of Building 'C' as well as flattened out the area for Utek's crane.

Windows were delivered on site for Building 'A'

Sub Meeting:
I met with Jesse (Diamond Z Stone) we discussed the stone caps on the chimney and angled columns.  Jesse asked if the chimney and or chimney cap could be smaller than what the plans showed.  We decided that we had better just stick with the plans so there would be no problems with framing or steel.  Although, we are going to slope the caps to keep water out of the chimney.
We also looked though the plans for anything that called out a sill on top of the windows and could not find anything.