Subs on Site
<LKL> (5)
<Reliance> (6)
<Utek> (22)
<Red Oak Plumbing> (7)
<DG Concrete> (2)
Work in Progress:

(Reliance)finished pulling wire in all of Building 'A' 1st floor units and started make up
Bryson (Reliance) met with Rodney Bell (Strata) to discuss low voltage. Reliance will send me report of what they decided.
(Utek) Finished the 2nd floor walls on Building 'D'. Started 2nd floor walls on Building 'E' finishing one unit. Worked on prefab for Building 'C' 3rd floor. Hung 75% of the Windows on Building 'A'.
(Red Oak Plumbing) worked on the Gas lines and Water Supply lines for 1st and 2nd floors of Building 'A'
(DG Concrete) Built rock walls on the North end of Building 'A' and the first Window Well for the patios on the North end of the West side.
(CR Doors)delivered all but 4 of the HM Door frames.
Sub Meeting:
Randy (Warburtons) and Shad (DG Concrete) discussed leaving the West center section level for the frist week of Siding so that Warburtons can side that section before rock wall make access harder. I spoke with Caleb King (LKL) to make sure that all drywall is securely covered before the storm comes in tomorrow morning.
Randy (Warburtons) and Shad (DG Concrete) discussed leaving the West center section level for the frist week of Siding so that Warburtons can side that section before rock wall make access harder. I spoke with Caleb King (LKL) to make sure that all drywall is securely covered before the storm comes in tomorrow morning.