Weather: Sunny 38˚/19˚
Subs on Site
<Warburtons> (3)
<Standard Builders> (3)
<Diamond Z> (2)
<Air Doctors> (3)
<Reliance> (6)
<Utek> (17)
<Red Oak Plumbing> (4)
<DG Concrete> (2)
Work in Progress:
(Warburtons) started drying in Building 'C' garage.
(Standard Builders) Delivered their camper trailer. Spread out all the metal door frames for Building 'A'. The first door they set was framed 1/4" smaller than their rough opening should have been. Joe (Standard Builders) express concern about setting the doors if all of them are too small. We talked with Alma (Utek) if any of the doors will not fit Alma will make the adjustments.
(Diamond Z) went over the layout of the stone and got ready to dry in tomorrow. Jesse says that the side walls of the patios were excluded from his bid
(Air Doctors) finished the fire caulking including adding caulk on the floor side of the flue penetrations.
(Reliance) swept out the 1st floor, finished fire caulking, and boxed on the 2nd floor.
(Utek) finished straps on the exterior of Building 'E'. Continued the pre fab of Building 'C' 3rd Floor. Built the wood columns around the entry gables for Building 'A'.
(DG Concrete) worked on the rock walls on the North West corner of Building 'A'
Sub Meeting:
11/12/2012-
Bryson (Reliance)
Jesse (Diamond Z)
Jesse (Utek)
Alma (Utek)
Shad (DG Concrete)
William (Air Doctors) late
Pre-Rock inspection schedule (We will be insulating the whole unit after this inspection)-
The lower stairs for Building 'C', 'D', and 'E' will be here 11/19.
The stone will have the scratch coat on by the end of the week. We discussed the siding starting and focusing on the East center section. So that the ground can be flat until they finish. The stone will follow behind the excavators rock walls.
William (Air Doctors)said he should have more guys when we start ducting the floors and that their production should be 2-3 units/day.
Sub Meeting:
11/12/2012-
Bryson (Reliance)
Jesse (Diamond Z)
Jesse (Utek)
Alma (Utek)
Shad (DG Concrete)
William (Air Doctors) late
Pre-Rock inspection schedule (We will be insulating the whole unit after this inspection)-
- 1st floor 11/13/2012
- 2nd floor 11/15/2012
- 3rd floor 11/20/2012
- 4th floor 11/27/2012
The lower stairs for Building 'C', 'D', and 'E' will be here 11/19.
The stone will have the scratch coat on by the end of the week. We discussed the siding starting and focusing on the East center section. So that the ground can be flat until they finish. The stone will follow behind the excavators rock walls.
William (Air Doctors)said he should have more guys when we start ducting the floors and that their production should be 2-3 units/day.