Weather: Sunny 45˚/22˚
Subs on Site
<Warburtons> (4)
<Standard Builders> (3)
<Diamond Z> (5)
<Air Doctors> (3)
<Reliance> (6)
<Utek> (21)
<Red Oak Plumbing> (7)
<DG Concrete> (2)
Work in Progress:
(Inspections) Aaron (Uintah County) inspected and passed 2 of the 8 units on 1st floor of Building 'A'
as well as passing 7 of the 16 gas lines on the North end of Building 'A'
(Warburtons) worked on drying in Building 'C' garage. Stocked the material for Building 'A' roof. Started drying in Building 'A'
as well as passing 7 of the 16 gas lines on the North end of Building 'A'
(Warburtons) worked on drying in Building 'C' garage. Stocked the material for Building 'A' roof. Started drying in Building 'A'
(Standard Builders)Set the metal door frames we had to make up to 1/4" notches in the trimmers for a few of the doors to fit.
(Diamond Z) wrapped their tar paper and lath around Building 'A'
(Air Doctors) finished odds and ends with their line set including repairing the damage by other subs. They also worked on dryer boxes and exhaust vents on the top floor.
(Reliance) ran the 1 1/4" smurf tube for Strata and boxed 2nd floor units.
(Utek) framed the closets under the stairs for Building 'A'. Installed draft stops on Building 'D' & 'E'. Started setting sections of Building 'C' 3rd floor.