Friday 11/2/2012


 Weather: Sunny 61˚/36˚

Subs on Site
<RMP>                         (4)
<Diamond Z>                (6)
<Reliance>                    (5)
<Utek>                          (22)
<Red Oak Plumbing>     (5)

Work in Progress:
(Diamond Z) laid the brick for 4 1/2 of the 5 dumpster enclosures .

(Reliance) worked on panels and drilling out Building 'A'  1st floor.

(Utek)Framed the last unit on Building 'C' 2nd Floor and buttoned up the sheer.  Rolled the 2nd floor on Building 'E'. Sheeted Saturday.  Set all of the gables on the steel columns for Building 'A'.

(Red Oak Plumbing)ran the vent pipes for the rest of Building 'A'.

Pavement cracks sealed