Wednesday 10/31/2012

Weather: Sunny 64˚/32˚

Subs on Site
<Clegg Steel>               (1)
<Extreme Fire>             (3)
<Reliance>                    (4)
<Utek>                          (19)
<Red Oak>                    (8)
<Red Oak Plumbing>     (6)
<DG Concrete>             (2)

Work in Progress:
(Clegg Steel) Sent a man up with the embeds for the dumpster gates and to cut down the base plates

(Extreme Fire) worked on the North end units on 3rd and 4th floor.

(Reliance) pulled feeders to the panels on the top floors 

(Utek) sheeted the roof of building 'A', set 2 of 16 steel columns for the upper trusses, stood 2 1/2 units on Building 'C' second floor, rolled the 2nd floor on Building 'D', and worked on pre-fab.

(Red Oak)Poured the corridors and decks on the South end of Building 'A'


(Red Oak Plumbing) worked on the vents and drains for Building 'A' 2nd floor and started drilling for the gas mains on 1st floor.

(DG Concrete) Backfilled around Building 'A' then started rock walls behind Building 'C'