Monday 11/5/2012

 Weather: Sunny 60˚/30˚

Subs on Site
<Reliance>                    (5)
<Utek>                          (22)
<Red Oak Plumbing>     (5)
<DG Concrete>             (4)

Work in Progress:
(Reliance) Made up the panels on Building 'A' and drilled out.

(Utek)focused on Building 'A' portions of Less, Jesse, and Hyrum's crew joined in with Alma's crew and worked on the roof finishing the overbuilds and sheeting 1/2 of the South end.  Jesse took all of the framers not on the roof and worked on pick up for the North end interior.

(Red Oak Plumbing) drilled out the South end of 1st floor for Building 'A' for gas lines and main water lines.
 

(DG Concrete) continued on rock walls and sidewalks on the North side of Building 'C'.  We ran into trouble trying to fit window wells and the condensers in the center section.