Tuesday 10/9/2012





Weather: Sunny  70˚/38˚

Subs on Site
<Utek>                          (14)
<DG Concrete>            (2)

Work in Progress:
(Utek)Sheeted the South end of Building 'C', Started framing the center section, and buttoned up the garage walls and beams.  They also started prefabrication of the wall panels

(DG Concrete)Brought up the rest of the valve boxes to grade and finished the E-Fill for all of the road. They passed compaction on 1/2 of E-fill installed today.











Monday 10/8/2012



Weather: Sunny  65˚/34˚

Subs on Site
<Air Doctors>                (3)
<Utek>                          (6)
<DG Concrete>            (2)

Work in Progress:
(Air Doctors)Arrived this morning looked over the Building and remodeled their on site camp trailer.

(Utek)framed more walls on the Southern half of the first floor of Building 'B'

(DG Concrete)started on the valve boxes in the road.  They were called away at lunch to help Bob (DG Concrete) get ready for their asphalt because he made some sort of mistake.

Dennis (Ram) came by the site.  He was looking for the locks they had installed on the conex and fence around the lumber yard

Friday 10/5/2012



Weather: Sunny  65˚/36˚

 Subs on Site
<Utek>                         (15)

Work in Progress:
(Utek) Jesse (Utek)framed and sheeted the East side units on Building 'C' and Alma (Utek) finished framing Building 'C' garage walls and sheeted them


Thursday 10/4/2012


Weather: Sunny  62˚/34˚

Subs on Site
<Diamond Z>               (4)
<Utek>                         (15)
<DG Concrete>            (2)

Work in Progress:
(Diamond Z)finished all five of the dumpster enclosures up three courses so we  can tie in our curb and pour the slabs

(Utek)Was still waiting for studs so Alma (Utek) framed Building 'A' garage walls and started laying out for Building 'C' garage walls.

(DG Concrete)finished all the road base they had stocked on site and spread E-fill on the road East and South of the intersection.  They passed compaction.

Wednesday 10/3/2012


Weather: Sunny  79˚/41˚

Subs on Site
<Diamond Z)                 (4)
<Utek>                         (19)
<DG Concrete>            (2)

Work in Progress:
(Diamond Z) showed up in the afternoon and started stacking block on the dumpster enclosures

(Utek)Finished all detail work on the interior of Building 'A' and continued on the sheeting button up on the East side.  They also finished counting all the lumber on site and entered the counts onto a spreadsheet. Trusses were ordered and the ETA is 10/15

(DG Concrete) Installed road base along the rest of the road and failed compaction then failed the retest.  Ben (Horrocks) believes the proctor from the yard is wrong and took another sample to test

Matt(HUD) came and preformed the progress inspection.  I had to drive him to his car in Heber because his ride fell through.

Tuesday 10/2/2012



Weather: Sunny  80˚/45˚

Subs on Site
<Utek>                         (19)
<Red Oak>                   (6)
<DG Concrete>            (2)

Work in Progress:
(Utek)Stopped working on Building 'D' because there was not enough lumber to build 'C' and 'D'.  They continued to button up the sheeting on Building 'A'.  (Utek) Built a platform East of the Club House to build floor sections they can crane onto the walls on Building 'C' walls.  They got the exterior walls on the East end of Building 'C'.

(Red Oak) Poured Building 'B' garage floor and cut the Club House

(DG Concrete) Fixed the South 1/3 of the waterway between Building 'C' and 'B' garages where the concrete truck destroyed it.  They then installed road base from 2500 West to the intersection.

Monday 10/1/2012


Weather: Sunny  74˚/48˚

Subs on Site
<Clegg Steel>                (3)
<Utek>                         (14)
<Red Oak>                   (6)
<DG Concrete>            (2)

Work in Progress:
(Clegg Steel) Completed the stairs on the the South West and North West corners

(Utek)Buttoned up the some of the sheeting on Building 'A' and started chalking lines on Building 'C' and 'D'

(Red Oak) poured the Club House floor.  They did not inform me that they would be pouring today and Ben (Horrocks) did not make in time to test the concrete.

(DG Concrete)Finished the E-fill to the intersection and started spreading road base.  The process went faster with the road base being dumped on the road.


Friday 9/28/2012


Weather: Sunny 71˚/41˚

Subs on Site
<Utek>                         (10)
<DG Concrete>            (2)

Work in Progress:
(Utek) Started pick-up of the 1st level and continued framing the South end of the 4th floor.

(DG Concrete) Worked on the road from between Building 'B' & 'E' to

Thursday 9/27/2012


Weather: Cloudy 66˚/44˚

Subs on Site
<Utek>                         (10)
<DG Concrete>            (2)

Work in Progress:
(Utek) Started pick-up of the 1st level and continued framing the South end of the 4th floor. They also built the tapered columns on the exterior.

(DG Concrete)Had E-fill and Road base delivered and started down the road with E-fill from 2500 W to between Building 'B' and 'D' they will stay tomorrow to help get closer to Asphalt readiness

Wednesday 9/26/2012


Weather: Rain 64˚/35˚

Subs on Site
<Clegg Steel>               (3)
<Utek>                         (11)
<Red Oak>                   (7)
<DG Concrete>            (2)

Work in Progress:
It Rained all day.  The framers fork lift got stuck up to its axles.  Clegg Steel got shocked while trying to weld and the equipment tore up our E-fill in the parking lot and road.

(Clegg Steel) Installed stairs for the South West corner of Building 'A'

(Utek)Worked with Clegg Steel with their crane to set the stairs. And worked on interior walls and pick up for the 2nd Floor.

(DG Concrete) back filled on one corner of Building 'B' and cleaned up the track out on 2500 W over and over.