Tuesday 10/2/2012



Weather: Sunny  80˚/45˚

Subs on Site
<Utek>                         (19)
<Red Oak>                   (6)
<DG Concrete>            (2)

Work in Progress:
(Utek)Stopped working on Building 'D' because there was not enough lumber to build 'C' and 'D'.  They continued to button up the sheeting on Building 'A'.  (Utek) Built a platform East of the Club House to build floor sections they can crane onto the walls on Building 'C' walls.  They got the exterior walls on the East end of Building 'C'.

(Red Oak) Poured Building 'B' garage floor and cut the Club House

(DG Concrete) Fixed the South 1/3 of the waterway between Building 'C' and 'B' garages where the concrete truck destroyed it.  They then installed road base from 2500 West to the intersection.