Subs on Site
<Utek> (10)

Work in Progress:
(Utek) Started pick-up of the 1st level and continued framing the South end of the 4th floor. They also built the tapered columns on the exterior.
(DG Concrete)Had E-fill and Road base delivered and started down the road with E-fill from 2500 W to between Building 'B' and 'D' they will stay tomorrow to help get closer to Asphalt readiness