Friday 10/5/2012
Weather
: Sunny 65˚/36˚
Subs on Site
<Utek> (15)
Work in Progress:
(Utek) Jesse (Utek)framed and sheeted the East side units on Building 'C' and Alma (Utek) finished framing Building 'C' garage walls and sheeted them