Wednesday 9/26/2012


Weather: Rain 64˚/35˚

Subs on Site
<Clegg Steel>               (3)
<Utek>                         (11)
<Red Oak>                   (7)
<DG Concrete>            (2)

Work in Progress:
It Rained all day.  The framers fork lift got stuck up to its axles.  Clegg Steel got shocked while trying to weld and the equipment tore up our E-fill in the parking lot and road.

(Clegg Steel) Installed stairs for the South West corner of Building 'A'

(Utek)Worked with Clegg Steel with their crane to set the stairs. And worked on interior walls and pick up for the 2nd Floor.

(DG Concrete) back filled on one corner of Building 'B' and cleaned up the track out on 2500 W over and over.