Monday 10/1/2012


Weather: Sunny  74˚/48˚

Subs on Site
<Clegg Steel>                (3)
<Utek>                         (14)
<Red Oak>                   (6)
<DG Concrete>            (2)

Work in Progress:
(Clegg Steel) Completed the stairs on the the South West and North West corners

(Utek)Buttoned up the some of the sheeting on Building 'A' and started chalking lines on Building 'C' and 'D'

(Red Oak) poured the Club House floor.  They did not inform me that they would be pouring today and Ben (Horrocks) did not make in time to test the concrete.

(DG Concrete)Finished the E-fill to the intersection and started spreading road base.  The process went faster with the road base being dumped on the road.