Subs on Site
<Clegg Steel> (3)
<Utek> (14)
<Red Oak> (6)
<DG Concrete> (2)
Work in Progress:
(Clegg Steel) Completed the stairs on the the South West and North West corners
(Utek)Buttoned up the some of the sheeting on Building 'A' and started chalking lines on Building 'C' and 'D'

(DG Concrete)Finished the E-fill to the intersection and started spreading road base. The process went faster with the road base being dumped on the road.