Tuesday 10/9/2012





Weather: Sunny  70˚/38˚

Subs on Site
<Utek>                          (14)
<DG Concrete>            (2)

Work in Progress:
(Utek)Sheeted the South end of Building 'C', Started framing the center section, and buttoned up the garage walls and beams.  They also started prefabrication of the wall panels

(DG Concrete)Brought up the rest of the valve boxes to grade and finished the E-Fill for all of the road. They passed compaction on 1/2 of E-fill installed today.