Wednesday 10/3/2012


Weather: Sunny  79˚/41˚

Subs on Site
<Diamond Z)                 (4)
<Utek>                         (19)
<DG Concrete>            (2)

Work in Progress:
(Diamond Z) showed up in the afternoon and started stacking block on the dumpster enclosures

(Utek)Finished all detail work on the interior of Building 'A' and continued on the sheeting button up on the East side.  They also finished counting all the lumber on site and entered the counts onto a spreadsheet. Trusses were ordered and the ETA is 10/15

(DG Concrete) Installed road base along the rest of the road and failed compaction then failed the retest.  Ben (Horrocks) believes the proctor from the yard is wrong and took another sample to test

Matt(HUD) came and preformed the progress inspection.  I had to drive him to his car in Heber because his ride fell through.