Thursday 10/4/2012


Weather: Sunny  62˚/34˚

Subs on Site
<Diamond Z>               (4)
<Utek>                         (15)
<DG Concrete>            (2)

Work in Progress:
(Diamond Z)finished all five of the dumpster enclosures up three courses so we  can tie in our curb and pour the slabs

(Utek)Was still waiting for studs so Alma (Utek) framed Building 'A' garage walls and started laying out for Building 'C' garage walls.

(DG Concrete)finished all the road base they had stocked on site and spread E-fill on the road East and South of the intersection.  They passed compaction.