Friday 8/17/2012


Weather: Partly Cloudy  90˚/56˚

Subs on Site
<Sterns>                      (16)
<TouchStone>              (15)

Work in Progress:
(Sterns) slipped curb.  They started on the North end of Building 'A'

(TouchStone) Built and stood the exterior walls on Building 'A' 3rd floor.

I called to follow up Steve (Clegg Steel) and left a message asking for an on site meeting, for the stairs.  I talked and emailed Steve on 8/14 as well to request an on site meeting.

Thursday 8/16/2012


Weather: Partly Cloudy  90˚/59˚

Subs on Site
<Sterns>                      (12)
<TouchStone>              (16)
<DG Concrete>            (3)

Work in Progress:


 (Sterns) Strung the curb in the areas were it could be slipped.  They do not have a form for Reverse Curb so they will Curb catch until the hand poured sections.  Dennis (Sterns) told me 1/2 after the curb is slipped you can walk on it and he would guarantee we could drive on it by Monday.

(TouchStone) continued sheeting 3rd floor joists and started 3rd Floor walls at the South end.  They also worked on the deck walls on the 2nd floor

(DG Concrete) finished the last parts of curb and gutter then repaired were Questar trenched along the curb and gutter at the North end of Building 'A'.  When (Sterns) showed up we walked he site and touched up the road so the curb machine would run smooth.  (Sterns) did not want to shove the roof drain pipes through were the machine slipped the curb.  I spoke with Keith (DG Concrete) and we decided to move as many of the drains to were (Sterns) was hand poring the curb and core out where we would have to.  Keith would work out the cost with McKay.

Wednesday 8/15/2012


Weather: Partly Cloudy  88˚/56˚

Subs on Site
<TouchStone>              (16)
<Red Oak>                    (3)
<DG Concrete>            (3)

Work in Progress:
(TouchStone) continued to roll the 3rd floor joists and started sheeting at the South end.

(Red Oak) passed inspection on Building 'B' garage footings.

(DG Concrete) dug and filled Club House footings.  Tim installed the gravel around my drain boxes behind Building 'C' garage.


Tuesday 8/14/2012


Weather: Partly Cloudy  89˚/58˚

Subs on Site
<TouchStone>              (16)
<Reliance>                    (3)
<Red Oak>                    (3)
<DG Concrete>            (5)

Work in Progress:
(TouchStone) Finished framing the North end of the 2nd Floor.  Rolled Joists on the South end and laid out the middle section.

(Reliance) Back filled the secondaries around Building 'C', delivered another conex and made ready to leave.

(Red Oak) Tied all the rebar in Building 'B' garage footings.

(DG Concrete) Finished the curb and gutter on the whole site.  Installed the irrigation meters by Building 'D' and the Club house.  We laid out the Club House footings.  Tim and I laid out the drain boxes behind Building 'C' garage.

Monday 8/13/2012


Weather: Rain then Sunny  84˚/58˚

Subs on Site
<TouchStone>              (16)
<Reliance>                    (3)
<Red Oak>                    (3)
<DG Concrete>            (5)

Work in Progress:
(TouchStone) Continued framing the 2nd floor walls.  Laid out the 3rd floor and started cutting the TJI's

(Reliance) Dug secondaries for Building 'C'

(Red Oak) formed Building 'B' garage footings

(DG Concrete) Prepped the Curb and gutter around Building 'C' and in front of Building 'D'.  They also graveled the slab for Building 'D'.  We found the center of road hubs at each end of the section of road were we are graded too deep.  The sub base was graded right on at each end.  The hub in the middle was a cut and as such was dug out.  Chris (DG Concrete) said go ahead with the curb and we will look at the road later.  DG Concrete also pointed out that the sewer clean out for Building 'D' is in the parking stalls and there was a lot of ground water when Ether (Red Oak Plumbing) hooked up the sewer lateral.



Friday 8/10/2012


Weather: Partly Cloudy  92˚/61˚

Subs on Site
<TouchStone>              (13)
<Reliance>                    (3)
<Red Oak>                    (9)


Work in Progress:
(TouchStone) Continued framing the 2nd floor walls and cleaned the site.

(Reliance) worked on secondaries to Building 'C' and Building 'B'.

(Red Oak) poured the center section of Building 'C'.  Pass inspection and poured the 1st half of Building 'E' foundation walls.  Ben (Horrocks) told me they had a 7 1/2" slump.

Thursday 8/9/2012


Weather: Partly Cloudy  96˚/65˚

Subs on Site
<TouchStone>              (13)
<Reliance>                    (3)
<Red Oak Plumbing>   (3)
<Red Oak>                    (9)
<DG Concrete>            (5)

Work in Progress:
(TouchStone) Continued framing the 2nd floor walls and made up all of the headers they will need..  We discovered a problem with the decks were the concrete would only be 2" thick if we had full slope.  We will now set the decks an 1 1/2" lower so the concrete will contain the slope.

(Reliance) Backfilled their trenches around Building 'C' and Fixed their conduit in front of Building 'D' that Ether (Red Oak Plumbing0 damaged.


(Red Oak Plumbing) Passed inspection on the underground in Building 'E' and started backfill

(Red Oak) poured the patios and breeze ways in Building 'C' Finished prep for the center section of Building 'C'.  They also started setting forms on Building 'E' foundation walls.

(DG Concrete) Finished all of the curb and gutter we still had stakes for and made me a list of stakes needed.  Finished the grade and gravel for Building 'C' Garage and Backfilled around Building 'D'






Wednesday 8/8/2012


Weather: Sunny  93˚/57˚

Subs on Site
<TouchStone>              (13)
<Reliance>                    (3)
<Red Oak Plumbing>   (3)
<Red Oak>                    (9)
<DG Concrete>            (5)

Work in Progress:
(TouchStone) Started framing the 2nd floor walls and figured out the Stair holes.

(Reliance) Poured the last 4 light poles and continued with the primaries in front of Building 'C'

(Red Oak Plumbing) Installed the floor drains in Building 'C' before the 4 AM pour then finished plumbing Building 'D' and tested it.

(Red Oak) Pour each end of Building 'C' at 4 AM.  Then formed the breezeways and patios and started on 1/2 of Building 'E' foundation walls.

(DG Concrete) graded and graveled Building 'A' garage,  graded more curb and gutter, and graded Building 'C' garage.


Tuesday 8/7/2012


Weather: Sunny  93˚/59˚

Subs on Site
<TouchStone>              (13)
<Reliance>                    (3)
<Red Oak Plumbing>   (3)
<Red Oak>                    (9)
<DG Concrete>            (5)



Work in Progress:
(Touchstone)Sheeted the 2nd floor.  Finished the interior walls and sheeting on the 1st Floor.

(Reliance) Trenched for light poles and primaries around Building 'D'&'E' and pass inspection on the last of the light poles.

(Red Oak Plumbing) Plumbed Building 'D' inspection on Thursday

(Red Oak) Installed and passed inspection on Building 'C' slab rebar

(DG Concrete) finished graveling Building 'C', Graded for curb and gutter on the islands in Building 'A' parking lot, and started grading Building 'A' garage floor.


Monday 8/6/2012



Weather: Partly Cloudy/Rain  89˚/59˚

Subs on Site
<TouchStone>              (13)
<Reliance>                    (3)
<Red Oak Plumbing>   (2)
<Red Oak>                    (9)
<DG Concrete>            (5)



Work in Progress:
(Touchstone) rolled the joists for the middle and North section of Building 'A'.  Buttoned up the sheeting and interiors on the North end of Building 'A'

(Reliance) readied 6 light poles for inspection and pour tomorrow.

(Red Oak Plumbing) finished the last run of plumbing in Building 'C' after the fittings were delivered by Fed-Ex.  They cleaned up their back fill and moved down to Building 'D',  where Ether (Red Oak Plumbing) offered use of his mini-ex to speed the backfill.

(Red Oak) Poured Building 'E' footings, started forming Building 'B' garage footings, and tieing bar in Building 'C' floor.

(DG Concrete) Started back filling Building 'D'.  Charlie (Red Oak) asked that they final grade Building 'C' for his pour.  They graveled 1/2 of Building 'C'.  Ether (Red Oak Plumbing) let DG Concrete use his mini to finish back fill on Building 'D'.