Friday 8/17/2012


Weather: Partly Cloudy  90˚/56˚

Subs on Site
<Sterns>                      (16)
<TouchStone>              (15)

Work in Progress:
(Sterns) slipped curb.  They started on the North end of Building 'A'

(TouchStone) Built and stood the exterior walls on Building 'A' 3rd floor.

I called to follow up Steve (Clegg Steel) and left a message asking for an on site meeting, for the stairs.  I talked and emailed Steve on 8/14 as well to request an on site meeting.